RERC · Rajasthan Electricity Regulatory Commission
Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework Regulations, 2010
Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010
FrameworkDated 23 Dec 2010No.RERC/Secy/Reg. 82 dated 23rd December, 2010
Replaced by Rajasthan Renewable Purchase Obligation Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Rajasthan Commission's 23 December 2010 notification creating the state's framework for meeting renewable purchase obligations through Renewable Energy Certificates. It was made under sections 61, 66, 86(1)(e) and 181 of the Electricity Act 2003 and applies throughout Rajasthan (p1).
The regulations bind the "obligated entities" already identified in the RERC (Renewable Energy Obligation) Regulations, 2007 — distribution licensees including deemed licensees, open access consumers, and captive consumers of captive plants of 1 MW and above (p1). Definitions in regulation 3 fix the vocabulary for the whole framework, including what counts as an obligated entity's consumption, the pooled cost of power purchase, preferential tariff, floor and forbearance prices, and the roles of the Central Agency, Central Commission and State Agency (pp1–4).
Regulation 4 does not itself set the obligation percentages: it requires obligated entities to procure renewable energy per the existing regulations and orders, and reproduces the then-current obligation structure for distribution licensees (wind and biomass; solar, excluding capacity under the Government of India's GBI/incentive scheme) and for captive and open access consumers (p4). Regulation 5 makes CERC-issued certificates a valid compliance instrument alongside direct purchase of renewable energy, with the key restrictions that solar and non-solar obligations must be met by the matching certificate type and that the biomass purchase obligation cannot be discharged through RECs (p5). Regulation 6 assigns the State Agency its information-collection, quarterly reporting and website-posting duties (pp5–7).
Regulation 7 governs purchase, credits excess purchases to the following year, allows a shortfall to be made up to 30 June of the next financial year, requires licensees to show estimated renewable purchase in their tariff/ARR petitions, and requires an auditor-certified annual statement by 30 September (p7). Regulation 8 fixes the operating period of the REC framework until 31 March 2016 (p7). Regulation 9 sets the consequences of default — an RPO charge on the shortfall into a dedicated fund, use of that fund, penalty under section 142 with no pass-through for licensees, and the possibility of carry-forward or waiver where genuine difficulty is shown (pp7–8). Regulation 10 splits REC pricing into the electricity component and the certificate: pooled cost of power purchase for discoms (with a petition and order cycle and provisional pricing), mutually agreed price for open access and captive users, and exchange-discovered REC prices subject to CERC floor and forbearance prices (pp8–9). Regulations 11 and 12 protect existing renewable projects under existing tariff orders and give new projects a choice between preferential tariff and the REC route, with switching rules (pp9–10). SLDC must follow the CERC REC procedure (p10); the Commission retains amendment and difficulty-removal powers, and regulation 16 repeals regulation 5 of the 2007 Renewable Energy Obligation Regulations with savings (pp10–11).
Read with this
Amendments and corrections
- Dated 15 Mar 2016Renewable Energy Certificate and RPO Compliance Framework Regulations, 2010 — First Amendment, 2016
- Dated 7 Jun 2017Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework (Second Amendment) Regulations, 2017
- Dated 5 Mar 2019REC and RPO Compliance Framework (Third Amendment) Regulations, 2019
Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.