RERC · Rajasthan Electricity Regulatory Commission
Renewable Energy Certificate and RPO Compliance Framework Regulations, 2010 — First Amendment, 2016
Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) (First Amendment) Regulations, 2016
AmendmentDated 15 Mar 2016In force from 1 Apr 2016No.RERC/Secy./Regulation -116 dated March 15, 2016
Replaced by Rajasthan Renewable Purchase Obligation Regulations, 2023
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework Regulations, 2010.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to the Rajasthan Electricity Regulatory Commission (Renewable Energy Certificate and Renewable Purchase Obligation Compliance Framework) Regulations, 2010, issued by the Commission on 15 March 2016 and brought into force from 1 April 2016 (p1). It does three operative things.
First, it replaces Regulation 4 of the Principal Regulations, restating the Renewable Purchase Obligation for 'Obligated Entities' but no longer fixing the obligation itself in this framework: distribution licensees are referred to the RERC Power Purchase & Procurement Process of Distribution Licensee Regulations, 2004, and captive consumers of CPPs and open access consumers are referred to the RERC (Renewable Energy Obligation) Regulations, 2007, each as amended from time to time (p1–2).
Second, it deletes Regulation 8 of the Principal Regulations outright (p2).
Third, it substitutes Regulation 9(1), setting out the compliance cycle: quarterly reporting by obligated entities with final annual accounts by 31 July of the Assessment Year; shortfall assessment by the State Agency; default notices by 30 September; payment of RPO charge by 30 November, computed from the shortfall and the solar or non-solar REC forbearance price; and onward transfer of the sums to a fund with the STU for renewable-evacuation transmission infrastructure or renewable promotion as approved by the Commission, with a petition to the Commission by 31 December recommending penal action (p2–3). An Explanation defines Relevant Financial Year, Assessment Year and forbearance price (p3).
Read with this
The regulation
Amendments and corrections
Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.