KSERC · Kerala State Electricity Regulatory Commission
Terms and Conditions for Determination of Tariff Regulations, 2018 — First Amendment, 2020
The Kerala State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (First Amendment) Regulations, 2020
AmendmentDated 13 May 2020Published in the Gazette 11 May 2020No. 659/D(T)/2019/KSERC dated 13th May, 2020
Replaced by Terms and Conditions for Determination of Tariff Regulations, 2021
See that regulation for the date it took effect and for anything it keeps in force.
Amends a regulation Voltaic does not hold.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal,- (i) Any proceedings before the Commission pertaining to the period till March 31, 2022, including determination of tariff or truing up or review matters pertaining to the period upto 31st March 2022, shall be governed by the *Kerala State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2018, the Kerala State Electricity Regulatory Commission (Terms and Conditions of Tariff for Retail Sale of Electricity) Regulations, 2006*”
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a single-clause amendment by the Kerala State Electricity Regulatory Commission to its 2018 Tariff Regulations, changing one thing: the size of capital investment scheme that a distribution licensee must put to the Commission for prior approval with a Detailed Project Report. The notification itself (p1) records the enabling power under Regulation 95 of the 2018 Tariff Regulations read with s.181 of the Electricity Act, 2003, and is numbered No. 659/D(T)/2019/KSERC, dated 13 May 2020, published in the Kerala Gazette Extraordinary dated 11 May 2020.
Regulation 1 (p2) gives the short title and says the amendment takes effect from the date of publication in the Official Gazette. Regulation 2 (p2–3) substitutes Clause C of Annexure IV, 'Guidelines for in principle clearance of investment scheme', of the 2018 Regulations. Where the old clause set one threshold for KSEB Ltd and another for all other distribution licensees, the new clause sets three licensee-specific thresholds — KSEB Ltd, the named licensees KDHPCL, TCED and CPT, and other distribution licensees — above which separate capital investment schemes with DPRs must be filed for approval. The substituted clause also states what the DPR must contain (cost-benefit analysis, funding details, least-cost investment plan, scope, objective and evaluation criteria) and adds two provisos: one for emergency works already under way or completed, and one allowing works below the thresholds without prior approval, subject to prudence check in truing up.
The Explanatory Note (pp3–4) explains the trigger: a petition from M/s Cochin Special Economic Zone Authority (CSEZA), one of the licensees, to revise the Annexure IV limits; a 2019 draft amendment circulated for comments and a public hearing at CSEZA, Kakkanad on 15 November 2019. For an analyst, this matters only as a threshold-setting amendment to the KSERC capital-investment approval gateway.
Read with this
Voltaic does not hold the regulation itself.
Other copies of these documents (1)
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.