Skip to content

KSERC · Kerala State Electricity Regulatory Commission

Terms and Conditions for Determination of Tariff Regulations, 2018 — First Amendment, 2020

the Kerala State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (First Amendment) Regulations , 2020

Gazette copyDated 13 Feb 2020No. 659/D(T)/2019/KSERC dated 13.02.2020

Replaced by Terms and Conditions for Determination of Tariff Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

A Gazette copy of a regulation Voltaic does not hold or of one of its amendments.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal,- (i) Any proceedings before the Commission pertaining to the period till March 31, 2022, including determination of tariff or truing up or review matters pertaining to the period upto 31st March 2022, shall be governed by the *Kerala State Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) Regulations, 2018, the Kerala State Electricity Regulatory Commission (Terms and Conditions of Tariff for Retail Sale of Electricity) Regulations, 2006*”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on dev.erckerala.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a two-page KSERC notification amending Annexure IV, Clause C of the KSERC (Terms and Conditions for Determination of Tariff) Regulations, 2018, issued as No. 659/D(T)/2019/KSERC and dated 13 February 2020 (p1). The substituted Clause C replaces the single earlier monetary threshold for submitting Detailed Project Reports (DPRs) with per-licensee capital-investment limits: KSEB Ltd., KDHPCL/TCED/CPT, and other distribution licensees each get their own ceiling above which a separate capital investment scheme with a DPR needs the Commission's approval (p1-2).

The new clause restates the content requirements for DPRs (cost-benefit analysis, funding details, least-cost plan, scope/objective, and evaluation criteria) and adds two provisos: one allowing a licensee to seek approval during or immediately after emergency work that was not previously approved, and one allowing works within the financial limits and done without prior approval to be approved at truing up after a prudence check (p2).

The Explanatory Note records the origin of the change: a petition from M/s Cochin Special Economic Zone Authority (CSEZA, one of the licensees), a draft First Amendment published in 2019 for stakeholder comments, and a public hearing at CSEZA, Kakkanad on 15 November 2019 (p2). The amendment takes effect from Gazette publication, but the Gazette date is not printed (p1).

Standard name
Tariff Regulations
Primary topics
Capital cost and investment, ARR and true-up

Read with this

Voltaic does not hold the regulation itself.

One more document belongs here and is not on Voltaic: a copy in another language.

Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page