CERC · Central Electricity Regulatory Commission
Guidelines for Virtual Power Purchase Agreements
RegulationDated 24 Dec 2025Published in the Gazette 28 Jan 2026F. No. L-1/257/2020/(PMR-4)/CERC dated 24th December, 2025
Summary
Summary written by software. Check the regulator's original before you rely on it.
These are CERC's Guidelines for Virtual Power Purchase Agreements, issued on 24 December 2025 and published in the Gazette on 28 January 2026 (p5, p1). They create a framework for VPPAs as non-transferable specific delivery (NTSD) over-the-counter contracts between a Consumer or Designated Consumer and a Renewable Energy Generating Station (REGS), principally to help designated consumers meet Renewable Consumption Obligation/Renewable Purchase Obligation targets (p5–6).
The Introduction (p5) sets out the policy context: Central Government RCO targets under the Energy Conservation Act, 2001, SEBI's opinion that VPPAs are bilateral OTC contracts outside SCRA, and MoP's request to CERC to devise a regulatory framework. The enabling power is Regulation 54(3) of the CERC Power Market Regulations, 2021 (p5).
Sections 2–4 (p5–6) give the short title, state that the Guidelines take effect from a date to be notified separately, apply to VPPA parties, describe the scope as the statutory framework for VPPAs, and define key terms including VPPA, VPPA Strike Price, Settlement Price, REGS, RCO, RPO, RECs and OTC contracts.
Section 5 (p6) lists essential VPPA features: electricity generated by REGS is sold through an authorised mode for physical delivery; RECs issued to REGS are transferred to the consumer; the contract is bilateral, non-tradable and non-transferable; and it must have a duration of at least one year. Section 6 (p7) covers implementation: VPPA as OTC contract, REGS registration under the REC Regulations, sale of electricity for purposes other than RPO/RCO compliance, transfer of RECs for compliance, and treatment on change of ownership.
Section 7 (p7) provides for bilateral settlement of the difference between VPPA Strike Price and Settlement Price. Section 8 (p7) deals with RECs: eligibility, an undertaking to the REC Registry to avoid double accounting, transfer to the consumer, extinguishment once transferred, carry-forward of surplus certificates, and registry communication. Section 9 (p7) leaves disputes to mutual settlement under the contract. The Hindi version appears at pp1–4, with the English text at pp5–7.
Read with this
Proposed changes (drafts with no final yet)
- Released with the notice dated 22 May 2025Guidelines for Virtual Power Purchase Agreements — Draft
- Dated 22 May 2025Public notice: Public Notice on Draft Guidelines for Virtual Power Purchase Agreements, 2025
- Dated 20 Jun 2025Notice extending the date for comments: Draft VPPA Guidelines — Comment Deadline Extension Public Notice
One more document belongs here and is not on Voltaic: a draft or notice on a draft.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of CERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.