Standards of Performance of Distribution Licensees (First Amendment) Regulations, 2017 — Explanatory Memorandum — Draft
DRAFT MERC (STANDARDS OF PERFORMANCE OF DISTRIBUTION LICENSEES, PERIOD FOR GIVING SUPPLY AND DETERMINATION OF COMPENSATION) (FIRST AMENDMENT) REGULATIONS, 2017
Explanatory memorandum to a draftDated 2 Aug 2017
Draft
Voltaic holds no final regulation made from this draft.
Explanatory memorandum to the Standards of Performance of Distribution Licensees, Period for Giving Supply and Determination of Compensation, 2014 — First Amendment, 2017 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This two-page explanatory memorandum from the Maharashtra Electricity Regulatory Commission explains why the Commission proposes to amend the load limit for releasing new connections on low-tension (LT) lines, and sets out the exact clause it intends to substitute (p1–2). It is a consultation-stage document, not the amendment itself.
Paragraph 1 recites the existing position. Regulation 5.3(a)(ii) of the 2014 Standards of Performance of Distribution Licensees Regulations classifies installations by contract demand and fixes the voltage at which they connect; for LT lines the cap on contract demand is 80 kW / 100 kVA in general areas and 150 kW / 187 kVA in Municipal Corporation areas, with a higher proviso limit for multiple consumers supplied at a single point in the same premises in Corporation areas (p1).
Paragraph 2 gives the history. MSEDCL sought to raise the non-Corporation limit to match the Corporation limit; the Commission rejected that petition on 16 May 2016, but on review (Case No. 151 of 2016) held on 26 July 2017 that rapid urbanisation and space constraints around Municipal Corporations and in urban and semi-urban areas justified revisiting the limit, subject to technical feasibility, through a public consultation (p1–2).
Paragraph 3 contains the proposal: substitute Regulation 5.3(a)(ii) with a single 150 kW / 187 kVA limit applying in all areas, plus a proviso allowing up to 480 kW / 600 kVA where multiple consumers in the same building or premises have cumulative contract demand above 150 kW / 187 kVA (p2). No commencement date, no savings clause and no enabling provision are stated, and no deadline for comments is given.
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
- Released with the notice dated 2 Aug 2017Standards of Performance of Distribution Licensees, Period for Giving Supply and Determination of Compensation, 2014 — First Amendment, 2017 — Draft
- Dated 2 Aug 2017Public notice: Public Notice — Proposed Amendment to Standards of Performance of Distribution Licensees Regulations, 2014
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.