Standards of Performance of Distribution Licensees (First Amendment) Regulations, 2017 — Explanatory Memorandum — Draft

DRAFT MERC (STANDARDS OF PERFORMANCE OF DISTRIBUTION LICENSEES, PERIOD FOR GIVING SUPPLY AND DETERMINATION OF COMPENSATION) (FIRST AMENDMENT) REGULATIONS, 2017

Explanatory memorandum to a draftDated 2 Aug 2017

Draft

Voltaic holds no final regulation made from this draft.

Explanatory memorandum to the Standards of Performance of Distribution Licensees, Period for Giving Supply and Determination of Compensation, 2014 — First Amendment, 2017 — Draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on merc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This two-page explanatory memorandum from the Maharashtra Electricity Regulatory Commission explains why the Commission proposes to amend the load limit for releasing new connections on low-tension (LT) lines, and sets out the exact clause it intends to substitute (p1–2). It is a consultation-stage document, not the amendment itself.

Paragraph 1 recites the existing position. Regulation 5.3(a)(ii) of the 2014 Standards of Performance of Distribution Licensees Regulations classifies installations by contract demand and fixes the voltage at which they connect; for LT lines the cap on contract demand is 80 kW / 100 kVA in general areas and 150 kW / 187 kVA in Municipal Corporation areas, with a higher proviso limit for multiple consumers supplied at a single point in the same premises in Corporation areas (p1).

Paragraph 2 gives the history. MSEDCL sought to raise the non-Corporation limit to match the Corporation limit; the Commission rejected that petition on 16 May 2016, but on review (Case No. 151 of 2016) held on 26 July 2017 that rapid urbanisation and space constraints around Municipal Corporations and in urban and semi-urban areas justified revisiting the limit, subject to technical feasibility, through a public consultation (p1–2).

Paragraph 3 contains the proposal: substitute Regulation 5.3(a)(ii) with a single 150 kW / 187 kVA limit applying in all areas, plus a proviso allowing up to 480 kW / 600 kVA where multiple consumers in the same building or premises have cumulative contract demand above 150 kW / 187 kVA (p2). No commencement date, no savings clause and no enabling provision are stated, and no deadline for comments is given.

Standard name
Standards of Performance
Primary topics
New connections and load changes

Read with this

Voltaic holds no final regulation made from this draft.

2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.

Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.