APERC · Andhra Pradesh Electricity Regulatory Commission
Framework for Resource Adequacy Regulation, 2026 — Statement of Reasons
In the matter of The Andhra Pradesh Electricity Regulatory Commission (Framework for Resource Adequacy) Regulation,2026 (Regulation No. 04 of 2026).
Statement of reasonsDated 25 May 2026
The commission's reasons for the Framework for Resource Adequacy, 2026 — Regulation 04.
Summary
Summary written by software, from pages 1 to 39 of 108. Check the regulator's original before you rely on it.
This is APERC's Statement of Reasons/Order for the Andhra Pradesh Electricity Regulatory Commission (Framework for Resource Adequacy) Regulation, 2026 (Regulation No. 04 of 2026), dated 25 May 2026 (p1). Pages 1–2 explain why the Commission is moving to a resource adequacy framework: Andhra Pradesh's Integrated Clean Energy Policy 2024 targets up to 160 GW of renewable capacity, with storage and decentralised RE programmes, while existing load-forecast and resource-plan arrangements (2000 Guidelines, Clause 9 of Regulation No. 4 of 2005, and the 27.06.2024 order for the 5th Control Period, FY 2024-25 to FY 2028-29) need a more granular framework. The draft regulation was posted for comments on 06.03.2026 (p1–2).
Pages 3–11 handle foundational clauses. The Commission rejects a five-year sunset (issue 1), retains the objectives (2), keeps applicability over generating companies, distribution licensees, SLDC, STU and other grid-connected entities (3), agrees to modify clause 3.2 to reference the December 2006 Guidelines while preserving the override of inconsistent earlier APERC regulations (4), and retains definitions of EENS and Net Load plus the distinction between planning horizons and procurement tenures (5–6). It keeps the RA framework stages and leaves tools/platforms to licensees (7–8), and retains demand forecasting/planning clauses without new network-planning mandates (9).
Pages 11–18 cover demand forecasting and data. Clause 6.3 is revised to require consumption/sales data by April 30 instead of April 21 (10). The DSM accounts clause is retained pending intra-state DSM regulations (11). Forecasting methodologies, database requirements, agricultural/policy parameters, load research/ToU impact assessment and short-term forecast clauses are retained (12–16).
Pages 18–21 retain SLDC state-level demand aggregation and STU state demand estimation (17–18) but widen clause 9.5 from 'state thermal generating companies' to all thermal generating companies in the State for flexible operation (19).
Pages 21–31 retain capacity crediting methodology and hydro/thermal factors (20–21), allow alternative methods such as ELCC with approval (22), keep CC factor submission dates (23–24), retain PRM clauses (25–27), keep scenario-based resource-gap analysis (28) and Annexure-I constraints (29), remove SLDC from transmission RA plan filing so STU alone files (30), and retain national peak contribution, ST-DRAP review and RPO/RCO/ESO treatment (31–33).
Pages 31–39 cover procurement and timelines. The Commission retains bidding guidelines and storage procurement, deletes bilateral contracts from clause 14.9, adds APERC Regulation No. 1 of 2022 references for short/medium-term and additional procurement (34–35, 38), retains prior approval for PPAs (36), rejects blanket pass-through of reserve-capacity fixed costs (37) and exemption from non-compliance charges (39), leaves the consumer-statistics clause unchanged (40), revises clause 21.1 to April 30 (41), adds August 30 distribution licensee LT-DRAP submission to SLDC and September 30 SLDC-to-CEA deadline (42), keeps the 15-day/October 30 LT-DRAP filing rule (43), and begins issue 44 on contracting balance capacity shortfall (44).
Read with this
The regulation
- Dated 26 May 2026Framework for Resource Adequacy, 2026 — Regulation 04
Earlier drafts
- Dated 6 Mar 2026Framework for Resource Adequacy Regulation, 2026 — Draft
Voltaic last read APERC's website for final documents on 24 Nov 2026 (2 pages) and for drafts on 21 Nov 2026. A document APERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.