NERC · Nagaland Electricity Regulatory Commission
Concept Paper on Road Map for Reduction of Surcharge and Cross Subsidies
Concept paper on "Road Map for reduction of Surcharge and Cross Subsidies"
Draft regulationDate not stated
Draft
A proposal, not law. Voltaic holds no final regulation made from this draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is a Nagaland Electricity Regulatory Commission concept paper on reducing surcharge and cross subsidies in Nagaland (p1). It begins by describing the Commission's constitution, its one-member structure and the Department of Power, Nagaland (DPN) as a deemed distribution licensee under Section 14 of the Electricity Act, 2003 (p1).
The paper then reviews the DPN's approved annual revenue requirements and tariff orders for FY 2011-12 and FY 2012-13. It tabulates revenue gaps, average cost of supply, cross subsidies by consumer category under existing and revised tariffs, and cross-subsidy levels in percentage terms (p3–10). It concludes that all consumer categories were being subsidised with State Government support, that no category was cross-subsidising another, and that revised tariffs reduced cross-subsidy levels (p11).
Section 6 proposes a road map of tariff as a percentage of cost of supply through 2017-18. It keeps small domestic BPL consumers and irrigation/agriculture consumers as subsidised, and says no category except commercial should be cross-subsidising at this stage; the road map is to be revisited after five years (p11–13). Section 7 gives an action plan focused on reducing cost of supply by lowering T&D losses, with a loss trajectory and steps on metering, billing, energy audit and sales growth (p13–15).
Section 8 reproduces Section 42(2) of the Electricity Act and Tariff Policy provisions on cross-subsidy surcharge and additional surcharge for open access, including the surcharge formula (p15–17). Applying that formula, the Commission concludes that the cross-subsidy surcharge for FY 2012-13 is negative, i.e. Nil (p18).
Read with this
The regulation
Voltaic last read NERC's website for final documents on 1 Oct 2026. A document NERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.