Summary
Summary written by software. Check the regulator's original before you rely on it.
This order is KSERC's decision to extend the life of its 2012 cross-subsidy reduction roadmap Regulations rather than let them lapse (p1, p3). The 2012 Regulations, notified on 20 November 2012 and valid for 60 months, set out the principles for determining cross-subsidy reduction and the roadmap for moving tariffs toward the cost of supply of the State's distribution licensees; the Commission says it has applied those principles in retail tariff design since FY 2013-14 (p1).
After the 60-month validity expired, the Commission reviewed actual cost coverage by consumer category from FY 2012-13 to FY 2017-18, set out in a category-wise table (p1). It finds industrial tariffs already within ±20% of average cost of supply, and domestic and street lighting moving toward that band, but says agriculture and commercial categories need more time and cannot be brought inside the band without tariff shock (p2). It therefore concludes a further 48 months are needed (p2). The ±20% band is described as mandated in the Tariff Policy (p2).
The Commission relies on Regulation 3(2) of the 2012 Regulations — which empowers it to extend validity beyond 60 months — together with s.181(1) and s.181(2)(j) and (zc) of the Electricity Act 2003 (p1, p2–3). By para 7 it extends the 2012 Regulations' validity by a further 48 months from 20.11.2017, i.e. backdated by about a month relative to the order date of 19.12.2017 (p3). No revised principles or new roadmap are issued here.
Read with this
The regulation
Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.