DERC · Delhi Electricity Regulatory Commission
Generation Tariff Regulations, 2011 (MYT FY 2012-15)
Delhi Electricity Regulatory Commission (Terms and Conditions for Determination of Generation Tariff) Regulations, 2011
RegulationDated 27 Feb 2011In force from 1 Apr 2012
Replaced by Terms and Conditions for Determination of Tariff Regulations, 2017
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software, from pages 1 to 34 of 39. Check the regulator's original before you rely on it.
This is DERC's principal generation-tariff regulation for Delhi, issued in December 2011 (p2) and in force from 1 April 2012 for three years, covering the Multi Year Tariff control period to 31 March 2015 (p3–4). It applies to determination of generation tariff under Section 62 of the Electricity Act 2003 for supply to a distribution licensee, and expressly does not apply where tariff was set through Section 63 bidding (p7). Existing tariffs approved or adopted under a PPA continue as approved for the existing installed capacity; new stations and post-1.4.2012 stations are governed by these Regulations (p7).
Chapter A2 defines the vocabulary of the regime (p3–7). Chapter A5 sets the MYT framework: a Commission-approved business plan for the whole control period, the applicant's tariff forecast, a performance trajectory and annual review; baseline values are set by the Commission, and controllable parameters are listed, with losses on them non-recoverable and gains retained by the generator (p8–9). Truing-up rules, including limits on interest-rate truing and exclusion of working-capital surpluses/deficits, sit here (p9).
Chapter A6 is the operative core — principles for admitting capital cost and additional capitalisation, debt-equity treatment (including the normative 70:30 for post-1.4.2012 capex and R&M), the renovation-and-modernisation/life-extension route and the special-allowance alternative for ageing coal units, interest and finance charges, working capital for coal versus gas stations, depreciation, return on equity, tax on income, normative O&M expense formulae and unit-size norms, and secondary fuel oil expense, adjustment and sharing (p10–21).
Chapter A7 fixes operational norms — plant-wise for the existing Delhi stations and generically for other stations — declares them ceiling norms that PPAs or agreements may improve upon, then gives the tariff mechanics: two-part tariff, the elements of fixed cost, capacity-charge formulae distinguishing stations under and over ten years of operation, energy-charge-rate formulae for coal and gas, landed cost of coal, built-in incentive, UI, deemed generation, billing and capacity-charge sharing, late payment surcharge, rebates and a safety manual requirement (p22–30). Chapters A8–A11 set the filing calendar (business plan, tariff applications 120 days ahead, provisional billing from 1.4.2012 pending approval, annual performance review and truing up with interest on refunds and recoveries), end-of-control-period review, disposal of applications within 120 days, periodic reviews, and miscellaneous provisions on CDM carbon-credit sharing and hedging of foreign-exchange variation (p30–34). The chapters address thermal stations — coal, gas and liquid fuel.
Read with this
Proposed changes (drafts with no final yet)
- Dated 4 Jul 2013Terms & Conditions for Determination of Generation Tariff, 2011 — First Amendment, 2013 — Draft
- Dated 4 Jul 2013Public notice: Generation Tariff (First Amendment) Regulations, 2013 — Public Notice
Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.