RERC · Rajasthan Electricity Regulatory Commission
Connectivity and Net Metering for Rooftop and Small Solar Grid Interactive Systems Regulations, 2015
Rajasthan Electricity Regulatory Commission (Connectivity and Net Metering for Rooftop and Small Solar Grid Interactive Systems) Regulations, 2015
RegulationDated 26 Feb 2015No. RERC/Secy/Reg. - 110 dated 26.02.2015
Replaced by Grid Interactive Distributed Renewable Energy Generating Systems Regulations, 2021
See that regulation for the date it took effect and for anything it keeps in force.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Rajasthan Electricity Regulatory Commission's framework for connectivity and net metering of grid-connected rooftop and small solar PV systems, notified at Jaipur on 26 February 2015 under section 181 read with sections 61, 66 and 86(1)(e) of the Electricity Act, 2003. Regulations 1–2 cover title, commencement on Gazette publication and definitions (pp1–4).
Regulations 3–6 set scope, eligibility and capacity: they apply to the distribution licensee and its consumers in Rajasthan, allow eligible consumers to install rooftop solar under net metering, require non-discriminatory first-come-first-serve access, cap aggregate capacity at a distribution transformer, cap individual plant size relative to sanctioned load/contract demand, set minimum and maximum plant sizes, and preserve alternative mechanisms for nodal agency/discom plants of 1 MWp and above (pp4–6).
Regulation 7 sets the application, feasibility, security-deposit and interconnection-agreement procedure with timelines (pp6–7). Regulations 8–9 adopt CEA technical standards and prescribe safety, protection, anti-islanding, synchronization and disconnection rules (pp7–12).
Regulation 10 is the commercial core: net-metering accounting, billing-cycle settlement, carry-forward of small credits, feed-in payment for larger exports, time-of-day treatment, exit credits and continuing fixed charges (pp12–14). Regulations 11–15 require annual reporting, allow eligible consumer solar generation to count toward the distribution licensee's solar RPO, exempt banking/wheeling/cross-subsidy surcharge, and prescribe metering and communication facilities (pp14–17). Regulations 16–20 cover CDM benefit pass-through, penalty, and Commission powers to direct, relax and amend (p17). Annexures provide abbreviations, standards references, application and acknowledgement formats, fee/security schedule, a model interconnection agreement, inverter/harmonics standards, interconnection schematics, net-metering configurations and meter specifications (pp18–33).
Read with this
Amendments and corrections
Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.