JSERC · Jharkhand State Electricity Regulatory Commission
State Grid Code, 2008 — 1st Amendment, 2019
Jharkhand State Electricity Regulatory Commission State Grid Code(1stAmendment) Regulations, 2019
AmendmentDated 4 Oct 2019Published in the Gazette 10 Oct 201968 dated 4th October, 2019
Amends the Jharkhand State Grid Code Regulations, 2008.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The JSERC State Grid Code (1st Amendment) Regulations, 2019 amend the Jharkhand State Electricity Regulatory Commission (State Grid Code) Regulations, 2008 and are notified by the Commission under section 181 of the Electricity Act 2003. The notification is dated 4 October 2019 and the regulations take effect from Gazette publication on 10 October 2019 (p1).
Section A gives the short title, extends the regulations to the whole State of Jharkhand, ties commencement to Gazette publication, and states that the amendments are limited to serial numbers 3 to 5 of the Principal Regulations (p1).
Section B replaces clause 3 (Part A: General). It restates who the State Grid Code applies to — SLDC, STU, intra-State transmission licensees, generating stations connected to the State grid, distribution licensees and users — with a proviso letting the Commission relieve a transmission licensee or user of code obligations, and a requirement that the code be construed consistently with the CERC Grid Code. Existing licensees and users get one year to enter connection agreements and develop Site Responsibility Schedules, single line diagrams and site common drawings (p1–2). Free Governor Action provisions are to apply on the same footing as the CERC Grid Code (p2).
Clause 4 requires the Commission to publish the code on its website and make copies available through SLDC and STU at no more than reproduction cost (p2).
Clause 5 constitutes a Grid Coordination Committee within 60 days, sets its membership — STU (Chairperson), SLDC (Convener), every generating company, transmission licensee, distribution licensee including deemed licensee, intra-State trading licensee, the State Government and Commission nominees — and lists its functions covering implementation, operational and commercial coordination, transmission planning and scheme review, data formats and energy accounting (p2–3).
Clauses 6 and 7 provide for monthly GCC meetings with minutes filed with the Commission, a quarterly grid code review report, and independent, autonomous functioning of the SLDC where it is operated by the STU (p3–4).
Read with this
The regulation
- Dated 30 Jan 2009Jharkhand State Grid Code Regulations, 2008