Skip to content

WBERC · West Bengal Electricity Regulatory Commission

State Electricity Grid Code Regulations, 2007

West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2007

RegulationDated 4 Apr 2007Published in the Gazette 4 Apr 2007No. 34/WBERC dated 04.04.2007

1 amendment to it is on Voltaic, dated 22 May 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on wberc.gov.in ↗

Summary

Summary written by software, from pages 1 to 15 of 29. Check the regulator's original before you rely on it.

Notification No. 34/WBERC dated 04.04.2007 makes the West Bengal Electricity Regulatory Commission (State Electricity Grid Code) Regulations, 2007 — short title WBEGC — and supersedes the Commission's earlier Notification No. 26/WBERC of 12 January 2006 (p1). It is framed under s.181(1) and s.181(2)(zp) read with s.86(1)(h) of the Electricity Act, 2003, takes effect from gazette publication, and applies concurrently across WBERC's jurisdiction (p1).

Chapter I (p1–5) is the general part. It sets out roughly seventy defined terms, the applicability rule — SLDC, ALDC and all entities connected to the State Grid, with the Central Grid Code and Grid Standards prevailing on inconsistency (p3) — and the objectives of the Code. It then allocates functional responsibilities among the STU, SLDC, distribution licensees, transmission licensees and generating stations, and provides for mandatory free governor operation of generating units above 50 MW, with a petition route for exemption and an exemption for gas turbines/CCGT and nuclear stations from the operation clauses (p5).

Chapter 2 (p5–8) governs State Transmission System planning: distribution licensees do the load forecasting that the STU consolidates into a 10-year State forecast plus a 5-year rolling plan, and it lays down planning criteria for distribution and transmission — voltage excursion limits, switchgear fault ratings, substation size caps, redundancy and contingency (n-1 type) standards the STS must withstand (p7–8).

Chapter 3 (p8–13) sets connectivity conditions: the application and offer procedure for new or modified connections, connection agreements and connection points, permissible frequency and voltage variation, equipment, protection and metering requirements by voltage class, data and communication obligations, reactive power compensation, Site Responsibility Schedules, single-line and site common drawings, and site access and maintenance standards. It also requires the STU to file an annual schedule of State grid assets (p13).

Chapter 4 covers operation of the State Grid: operation policy, system security including governor and AVR behaviour, deliberate isolation, tripping intimation, frequency band and voltage operating ranges, demand estimation, manual demand disconnection, load shedding and periodic reporting to the Commission.

Standard name
Grid Code
Primary topics
Grid operation and grid code, Network planning and investment, Connectivity and GNA

Read with this

Amendments and corrections

Voltaic last read WBERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document WBERC issued after the page that lists it was read may not be held by Voltaic yet.

As of its reading of WBERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on wberc.gov.in ↗

Report an issue with this document