MPERC · Madhya Pradesh Electricity Regulatory Commission
Capital Expenditure Guidelines for Distribution Licensees in Madhya Pradesh, 2025
Guidelines for Capital Expenditure by Distribution Licensees in Madhya Pradesh, 2025
GuidelinesDated 2 Jan 2025
Summary
Summary written by software. Check the regulator's original before you rely on it.
These are MPERC's 2025 Guidelines for Capital Expenditure by Distribution Licensees in Madhya Pradesh. They revise the 2005 guidelines and set the framework for distribution licensees to obtain the Commission's in-principle approval for proposed capital investments (p1).
Section 1 lists broad categories of capital investment schemes, including grant-funded schemes, new connections, system strengthening, agricultural connections, new substations/lines/transformers, quality and reliability works, SCADA and control/communication equipment, metering and protection, consumer services, asset replacement, DSM/renewable integration/energy conservation, smart grid, reactive power, civil works, storage, EV charging stations, microgrids, pilot emerging technologies, and any other schemes (pp1–2). It also requires a scheme-wise Detailed Project Report and lists evaluation parameters such as cost, time, IRR/payback, loss reduction, voltage profile, SAIFI/SAIDI, power quality, billing and collection efficiency, ARR impact, equipment failure rates, reactive power flow, automation/OPEX, online monitoring and consumer benefit (pp2–3).
Section 2 sets the approval framework. Schemes exceeding Rs 10 Crore require Commission approval; schemes of Rs 10 Crore or below require approval under the licensee's Delegation of Powers. Approval is two-stage: in-principle before works and final cost approval after the asset is put to use. Prior in-principle approval is not required for 100% grant-funded schemes or emergency works, but final approval still applies (pp3–4).
Section 3 lists what an in-principle petition must contain: scheme overview, justification, technical and financial analysis, cost-benefit analysis, monitoring methodology, statutory clearances, constraints and mitigation. The format is in Appendix 1/Annexure 1, which the Commission may modify or supplement by asking for more information. Section 4 provides for prudence check against Annexure 3 (pp4–6). Section 5 requires an annual rolling five-year capital investment plan by 1st October, comparing in-principle approved, revised, ongoing and new scheme costs, and including N-1 completed schemes for final cost approval. The Commission may return incomplete plans (pp6–7).
Repeal and saving: the 2005 guidelines are repealed for distribution licensees from the date of notification; they continue for transmission licensees until separate transmission guidelines are made; past actions under the repealed distribution guidelines are deemed valid (p7). Annexures 1–4 give filing formats and checklists for in-principle approval, rolling plans, technical and financial evaluation, and completed works, including justification for variations above 10% of approved cost and for time/cost overruns (pp8–14).
Read with this
Procedures and orders made under it
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.