CGRF and Ombudsman Regulations, 2005 — Amendment Regulations, 2020

Kerala State Electricity Regulatory Commission (Consumer Grievance Redressal Forum and Electricity Ombudsman) Amendment Regulations, 2020

AmendmentDated 18 Jun 2020Published in the Gazette 19 Jun 2020No. 1734/Admn/KSERC/2013 dated 18 th June, 2020

Replaced by Consumer Grievance Redressal Forum and Electricity Ombudsman Regulations, 2023

See that regulation for the date it took effect and for anything it keeps in force.

Amends a regulation Voltaic does not hold.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal,- (i) anything done or any action taken under the said Regulations shall be deemed to have been done or taken under the corresponding provisions of these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on dev.erckerala.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short KSERC amendment to its 2005 regulations governing Consumer Grievance Redressal Forums (CGRFs) and the Electricity Ombudsman in Kerala. The notification is dated 18 June 2020 and was carried in the Kerala Gazette Extraordinary on 19 June 2020 (p1); it comes into force at once (p2).

The operative part has two limbs (p2–3). The first substitutes clause (b) of regulation 3(3) of the 2005 Regulations, rewriting who the Commission may nominate as the Forum member: a law degree from a university recognised and approved by the Bar Council of India, at least three years' practice as an advocate before subordinate courts, and proven ability, integrity, standing and familiarity with consumer affairs. It sets the nomination term at three years and adds a proviso barring anyone who is or has been an employee of a distribution licensee (p2).

The second limb inserts a new regulation 3A, a validation clause deeming acts done by a member nominated for one year but who continued in office beyond that term to have been validly done, as if the term had been extended to the commencement date of these regulations (p2–3).

The Explanatory Note (p3–4), expressly not part of the notification, gives the background: section 42(5) of the Electricity Act 2003, the one-year term and general-degree qualification under the 2005 regulation, the Commission's decisions on tenure and qualification, the need to validate continuing members, and the public consultation on a draft published on 19 February 2019.

Standard name
CGRF and Ombudsman
Primary topics
Consumer grievance redressal (CGRF)

Read with this

Voltaic last read KSERC's website for final documents on 24 Nov 2026. A document KSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on dev.erckerala.org ↗

Report an issue with this document