Skip to content

MPERC · Madhya Pradesh Electricity Regulatory Commission

Details to be Furnished and Fee Payable for Tariff Determination Regulations, 2004 — Third Amendment, 2008

Madhya Pradesh Electricity Regulatory Commission (Details to be furnished and fee payable by Licensee or generating company for determination of tariff and manner of making application) Regulations, 2004 (Third Amendment) [AG-13(iii) of 2008]

AmendmentDated 19 Dec 2008Published in the Gazette 2 Jan 2009No. 2754-MPERC-2008 dated 19th December, 2008

Amends the Details to be Furnished and Fee Payable for Determination of Tariff and Manner of Making Application Regulations, 2004.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a short amendment by the Madhya Pradesh Electricity Regulatory Commission to its 2004 regulations governing the details to be furnished, and the fee payable, by a licensee or generating company applying for determination of tariff (p1). It is styled the Third Amendment, issued at Bhopal on 19 December 2008 and carried in the State gazette dated 2 January 2009, and it takes effect from that gazette publication (p1).

The operative change is a single new provision, Regulation 1.38A, inserted after Regulation 1.38 (p1). It requires the generating company, the transmission licensee and the distribution licensee each to file with the Commission an application for truing up of tariff orders the Commission has issued, and points each class of applicant to its own set of information formats — Annexure 5 for generating companies, Annexure 6 for the transmission licensee and Annexure 7 for the distribution licensee (p1).

Standard name
Tariff Regulations
Primary topics
ARR and true-up

Read with this

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on mperc.in ↗

Report an issue with this document