MPERC · Madhya Pradesh Electricity Regulatory Commission
Details to be Furnished and Fee Payable for Determination of Tariff and Manner of Making Application Regulations, 2004
Madhya Pradesh Electricity Regulatory Commission (Details to be furnished and fee payable by licensee or generating company for determination of tariff and manner of making application) Regulations, 2004
RegulationDated 13 Aug 2004No.2118/MPERC/2004
3 amendments to it are on Voltaic, the latest dated 19 Dec 2008.
A later regulation on Voltaic changes some of its provisions: Fees, Fines and Charges (Revision-II) Regulations, 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This 2004 MPERC regulation sets out the paperwork, fees and procedure by which generating companies and licensees in Madhya Pradesh apply for tariff determination, and how the Commission handles those applications (pp1–7). It also prunes the Commission's earlier fees regime.
Every generating company and licensee must file a tariff application by 15 November each year, showing expected revenues from the currently approved tariff and charges for the ensuing financial year with explanations of assumptions; a trading licensee files only when the Commission orders it to (p1). The information required is prescribed in four annexures — separate formats for generating companies, transmission licensees, distribution licensees and trading licensees (p1). Filings must carry a compliance statement on directives in the last tariff order, prior-year figures resting on audited accounts, and, for new entrants, an application on grant of licence or at least two months before commercial operation (pp1–2). A petition fee based on previous-year actuals applies (p2).
Transmission and distribution licensees must file voltage-wise technical and commercial loss statements, loss-reduction plans with investment needs for the ensuing year plus at least four more, and a plan to bridge any revenue gap (p3). Filings go in electronically as well, and each applicant must name a liaison working group (p3). After clarifications, the applicant publishes a Commission-approved summary in two local newspapers (English and Hindi), prints the application in two priced volumes, and makes it available at offices and on its website (pp3–4).
The Commission holds a hearing, then within 120 days of receipt must accept the application with modifications or conditions, or reject it with written reasons after a hearing (pp4–5). Orders go to the State Government, the CEA and the concerned companies within seven days (p5). Tariffs take effect seven days after newspaper publication of the tariff schedule, and any over-recovery is refundable with bank-rate interest (p5). Review lies within 60 days on error apparent on the record, and tariff may not be amended more than once a financial year except under adjustment formulae (pp5–6). The Commission may adopt multi-year tariff principles and issue filing guidelines (p6). It repeals listed items of the 2002 Fees and Charges Regulations and their Second Amendment (p6), and preserves its inherent powers and its ability to depart from these regulations for recorded reasons (pp6–7).
Read with this
Amendments and corrections
- Dated 26 Jul 2005Details to be Furnished and Fee Payable for Tariff Determination and Manner of Making Application Regulations, 2004 — Amendment, 2005
- Dated 22 Sep 2005Details to be Furnished and Fee Payable for Tariff Determination Regulations, 2004 — Second Amendment, 2005
- Dated 19 Dec 2008Details to be Furnished and Fee Payable for Tariff Determination Regulations, 2004 — Third Amendment, 2008
- Dated 27 Jun 2024Changes some provisions: Fees, Fines and Charges (Revision-II) Regulations, 2024
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.