The DERC (Business Plan) Regulations, 2019 (p2) are a three-year control-period instrument. Rather than setting tariffs, they fix the parameters the Commission will use to build tariffs and annual revenue requirements for Delhi's generators, transmitters and distribution licensees over FY 2020-21, FY 2021-22 and FY 2022-23 (p2). They are notified under s.181 read with s.61 and s.86(1)(b) of the Electricity Act, 2003, and take most of their operative content by cross-reference to the DERC (Terms and Conditions for Determination of Tariff) Regulations, 2017.
Part 1 (pp2–3) gives the short title, the three-year term (extendable at the Commission's discretion), Delhi-wide extent, and a definitions clause that imports the meanings used in the 2017 Tariff Regulations.
Part 2 (pp4–8) is the generating entity's business plan: how return on equity is computed and grossed up for tax, the margin allowed over SBI's one-year MCLR on loan interest, normative O&M expense rates, a tentative capital investment plan, operating norms (plant availability and load factor, gross station heat rate, auxiliary energy consumption), a generation incentive, a gain-sharing mechanism on controllable heat rate and auxiliary consumption, and sharing of re-financing gains.
Part 3 (pp9–13) mirrors this for the transmission licensee and adds a normative transmission availability factor, the monthly transmission-charge billing formula tied to availability, and cross-references to the availability computation in the appendices.
Part 4 (pp14–28) is the distribution plan, covering BRPL, BYPL, TPDDL and NDMC. It separates wheeling, retail and carrying-cost returns on equity, differentiates O&M norms by licensee and network element, adopts capitalisation plans, sets distribution-loss and collection-efficiency targets, sets renewable purchase obligation trajectories with compliance and penalty mechanics, imposes a deviation-settlement contingency limit, prescribes incentive sharing on surplus power sales, lays out the power purchase cost adjustment mechanism, fixes the ARR split between wheeling and retail business, and provides for true-up of revenue gap/surplus and ToD time slots.
Part 5 (pp29–30) is the standard machinery: orders and practice directions, removal of difficulties, relaxation, interpretation, inherent powers, enquiry procedure and amendment. Appendices I–III (pp31–35) set out the transmission availability computation procedure, surge impedance loading values, and the availability formulae.
Read with this
The regulation
- Dated 27 Dec 2019Business Plan Regulations, 2019
Commencement notices and reasons
- Dated 29 Jan 2020Business Plan Regulations, 2019 — Statement of Reasons
Proposed changes (drafts with no final yet)
Earlier drafts
- Dated 10 Dec 2019Explanatory Memorandum to Draft Business Plan Regulations, 2019
Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.