This is the Commission's principal regulation governing open access to, and connectivity with, the distribution systems of distribution licensees in Maharashtra, made under ss.2(47), 39(2)(d)(ii), 40(2)(c)(ii), 42(2)–(4) and 181 of the Electricity Act 2003 (p4). It applies both where a distribution network is used and where an open access consumer inside a licensee's area is supplied without using that licensee's network (p4). It takes effect on Gazette publication — the Gazette date is not printed (p4) — and it repeals the 2014 Regulations of the same name from the date of notification, with savings (p55–56).
Part A (pp4–13) sets the eligibility gate and the institutional machinery: definitions, the consumer contract-demand threshold for eligibility and the permitted 'Sources', the distribution licensee as Nodal Agency, application handling, settlement of dues and the final meter reading at switchover.
Part B (pp13–17) deals with connectivity: which generating stations may connect to the distribution system, the interconnection study against CEA technical standards, who bears augmentation cost, the Connection Agreement, and the rules for injecting infirm power before commercial operation.
Part C (pp17–31) is the procedural core: the open access agreement, categories by location of injection and drawal points and by duration, the application procedure (with inter-state applications routed to CERC's framework), separate long-term, medium-term and short-term procedures and timelines, bank guarantee for long-term applicants, electronic bidding where capacity is congested, the licensee's consent, and allotment priority.
Part D (pp32–38) prescribes the charge heads and billing mechanics — wheeling charges, cross-subsidy surcharge (discounted for renewable-sourced power), additional surcharge on stranded fixed costs, and additional security for wheeling. Part E (pp38–42) covers scheduling by MSLDC, Special Energy Meters with AMR and RTUs, and allocation of transmission and distribution losses. Part F (pp42–48) sets the deviation/imbalance settlement regime, renewable energy banking over the financial year with Time-of-Day drawal restrictions, and reactive energy charges.
Parts G to I (pp48–55) cover billing, collection and disbursement, late payment, default and disconnection, payment security, change of injection and drawal points, mandatory website disclosure, curtailment priority, preservation of existing contracts, an Open Access Monitoring and Review Committee, dispute adjudication by the Commission, force majeure, exemptions and the repeal-and-savings clause.
The five annexures (pp57–104) supply the operative paperwork: the connectivity application form, a full-form Connection Agreement, the short-term application/approval/bidding formats (ST1–ST4), the model long-term/medium-term application, and the long-term/medium-term Open Access Agreement with its augmentation annexures.
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
- Dated 16 Sep 2015Public notice: Public Notice — Comments on Draft Distribution Open Access Regulations, 2015
One more document belongs here and is not on Voltaic: a draft or notice on a draft not held as English text.
Voltaic last read MERC's website for final documents on 24 Nov 2026 (8 pages) and for drafts on 24 Nov 2026. A document MERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.