PSERC · Punjab State Electricity Regulatory Commission
Power Purchase and Procurement Process of Licensee Regulations, 2012
Punjab State Electricity Regulatory Commission (Power Purchase and Procurement Process of Licensee) Regulations, 2012
RegulationDated 23 Oct 2012PSERC/Secy/Regu.75 dated 23rd October, 2012
Replaced by Punjab Framework for Resource Adequacy Regulations, 2024
See that regulation for the date it took effect and for anything it keeps in force.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed Regulations shall deemed to have been done or purported to have been done under these Regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Punjab State Electricity Regulatory Commission issued these principal regulations on 23 October 2012 (p1) under ss 86(1)(b) and 181 of the Electricity Act, 2003. They apply to all inter-State and intra-State purchase and procurement of power by distribution licensees, including deemed licensees, in Punjab (p1). They come into force from the date of publication in the Punjab official gazette; the Gazette date is not printed (p1).
Regulations 1–3 set the title, commencement, definitions and scope: a distribution licensee must follow them when forecasting demand and energy, preparing procurement plans and actually procuring power (p1–3). Regulation 4 requires the licensee to assess demand and energy for the next year on a monthly basis and for ten years, using historical data, business plans, efficiency and DSM assumptions, open-access and captive migration, seasonal factors such as paddy and non-paddy periods, and CEA Electric Power Survey methodology (p3–4). Regulation 5 requires matching long- and short-term availability assessments from owned plants, BBMB, central-sector plants and other sources, banking arrangements and new stations (p5–6). Regulation 6 sets how availability is computed for hydro, thermal, gas, nuclear and NRSE/PEDA projects, including CEA norms, hydrological constraints and transmission-loss treatment (p6–7).
Regulation 7 requires a least-cost long-term rolling ten-year procurement plan and an annual short-term plan, both on a monthly basis; the long-term plan is part of the ARR and the first is due with ARR 2014-15 (p7–8). The short-term plan is due by 31 October and approved by 31 December, with the first plan due within 45 days of notification and approval within 30 days (p9). Regulation 8 permits additional procurement up to 10% of approved quantum without prior approval, and beyond that with Commission approval, which must decide in 30 days (p9–10). Regulation 9 details submission and approval of plans, possible public consultation and interim orders (p10–11). Regulation 10 requires purchases to follow approved plans and the least-cost principle, allows criteria for hydro, co-generation and renewables, requires consultation with STU, transmission licensees, generators, SLDC, NRLDC, CEA and others, and asks licensees to avoid reactive-power import from the Northern Grid (p11–12). Regulations 11–12 prescribe short-term procurement through competitive bidding under MoP guidelines dated 15 May 2012, power exchange or banking, and long-term procurement through competitive bidding under the 19 January 2005 guidelines or s62 tariff determination; legacy MOUs/PPAs before these regulations are excluded till their validity, and contracts over one year but under ten years are treated as long-term (p12–14). Regulation 13 requires prior Commission approval of new long-term PPAs and amendments against listed tests (p14). Regulation 14 limits Commission intervention in an ongoing procurement process except on specified grounds and provides investigation and nullification powers (p14–15). Regulations 15–16 give the Commission power to remove difficulties and to amend the regulations (p15).
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.