Power System Development Fund Regulations, 2019 — Draft

Central Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019

Draft regulationDated 24 May 2019No. L-1/247/2019/CERC dated the 24 th May, 2019

Draft

A proposal that has since been finalised as the Power System Development Fund Regulations, 2019.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft notification (No. L-1/247/2019/CERC) dated 24 May 2019 by which CERC proposes to replace its 2014 Power System Development Fund regulations with a new set of 2019 regulations, made under s.178(1) and s.178(2)(ze) of the Electricity Act, 2003 (p1). It runs to eight regulations across six pages and is complete in itself; commencement is tied to publication in the Official Gazette, whose date is not printed (p1).

Regulation 2 defines the fund's vocabulary and cross-refers to the congestion relief, power market, deviation settlement and grid code regulations that supply the charges flowing into the fund (p1–3). Regulation 3 constitutes the PSDF, lists the charge streams credited to it, obliges collecting agencies to transfer them periodically, and places the fund in the Public Account of India (p3–4).

Regulation 4 is the spending rule: assistance is grant-based and netted off project capital cost, and is confined to enumerated categories — strategic transmission, reactive compensation, protection schemes and protection audits, renovation and modernisation, and studies or capacity building — with a route for distribution utility projects incidental to the inter-State transmission system, a route for Central Government schemes, prioritisation by the Central Government, and an express exclusion of private sector projects (p4–5).

Regulation 5 makes NLDC the Nodal Agency, with a proviso letting the Central Government substitute another agency, and lists its record-keeping, budget/audit procedure, annual report and residual functions (p5). Regulation 6 leaves application, appraisal, sanction and disbursal procedure to Central Government guidelines, routes proposals through the Appraisal Committee and Monitoring Committee, obliges project entities to furnish project details, and places execution and O&M on the project entity for the asset's useful life (p5–6). Regulation 7 requires an annual PSDF report to the Central Government and the Commission, laid before both Houses of Parliament through the Ministry of Power (p6). Regulation 8 repeals the 2014 regulations with a savings clause preserving past actions (p6).

Primary topics
Power System Development Fund (PSDF), Capital cost and investment

Read with this

The regulation

Commencement notices and reasons

Other copies of these documents (1)

Earlier drafts

One more document belongs here and is not on Voltaic: a draft or notice on a draft.

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document