Summary
Summary written by software. Check the regulator's original before you rely on it.
Two notifications issued the same day under one cover. The first (No. KERC/OP06/2024/249, 24.06.2024, pp1–2) is the preamble and approving order: it records KPCL's petition OP 06/2021 seeking a scheduling and despatch procedure and a landed-cost basis for merit order, the public hearing held on 06.03.2023 on the 2022 draft, stakeholder comments, and the Commission's approval of the 2024 Regulations, citing ss.181/61/62/66 and s.86(1). The second (No. KERC/OP06/2024/250, pp3–20) is the operative regulation, in force from Gazette publication (p3).
Regulations 1–3 (pp3–7) give the title and commencement, a definitions set covering MOD and MOD Stack, declared capacity, on-bar/off-bar DC, hot/warm/cold start, technical minimum, must-run plants, AC-UBC, ATC/TTC and variable charges, and confine application to SLDC, all distribution licensees and generating companies including captive plants supplying licensees in Karnataka.
Regulation 4 (pp8–10) sets the principles for building the MOD stack at the State periphery — verification of variable cost, addition of inter-state transmission losses and common AC-UBC charges on an (n-1)-th month basis, submission to SLDC, grounds on which SLDC may revise the stack, change-in-law pass-through mechanics and the reprisal route (s.142 penalty) if a generator withholds revised variable charges.
Regulation 5 (p10) is a fortnightly calendar of data flow — generators' variable charges, licensees' verified submissions, and SLDC's stack preparation and website upload — and Regulation 6 (pp11–13) lays down the least-cost despatch principles: demand forecasting, cost minimisation including start-up/shut-down and part-load costs, avoiding load curtailment, unit commitment and ramp considerations, curtailment of must-run/intermittent RES with reasons, spinning reserve adequacy (FCR/FRR/RR), compliance with IEGC constraints, system/policy limits and market opportunities.
Regulations 7–11 (pp14–19) address operating practice: capacity declaration and fuel/water disclosure formats, SLDC's power to require demonstration of DC, ramp-rate declaration, mis-declaration monitoring and 'gaming' dashboards; zero scheduling of contracted sources and who bears its cost; instructing unit shut-down; revival from unit shut-down with hot/warm/cold start times and minimum run times; and technical minimum operation for intra-State thermal units with compensation for operating below normative availability. Regulations 12–15 (pp19–20) reserve the Commission's powers to amend, remove difficulties, relax and issue practice directions, codes or guidelines; Regulation 16 (p20) repeals earlier merit-order despatch regulations and orders with a savings clause. Annexure-1 (p21) is the fortnightly MOD stack format and Annexure-2 (p22) the backing-down report format.
Read with this
Other copies of these documents (1)
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.