Balancing & Settlement Mechanism for Open Access Regulations, 2010
Jharkhand State Electricity Regulatory Commission (Balancing & Settlement Mechanism for Open Access) Regulations, 2010
RegulationDated 27 Jan 2010Published in the Gazette 28 Jan 2010No. 23 dated The 27th January, 2010
A later regulation on Voltaic changes some of its provisions: Terms and Conditions for Intra-State Open Access Regulations, 2016.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The Jharkhand State Electricity Regulatory Commission's Balancing & Settlement Mechanism for Open Access Regulations, 2010 (Notification No. 23 dated 27 January 2010, published in the Jharkhand Gazette of 28 January 2010) is the state's rulebook for how energy scheduled and actually delivered under intra-state open access is accounted for, priced and settled among open access generators (OAGs), open access consumers (OACs), distribution licensees and SLDC. It extends to the whole state and comes into force on Gazette publication (p1).
Sections A1–A3 set commencement, definitions and scope: the mechanism binds OAGs and OACs (p1–6). A4 requires day-ahead, 15-minute-block injection/drawal schedules to SLDC and allows in-day revisions per the Grid Code; "uncontrollable" renewable sources are exempt from day-ahead scheduling, with actual metered generation treated as schedule and zero UI (p6). A5 lists which agreements must exist between OAC, licensee, transmission utility and generator, including where the OAG sits outside the state (p6).
A6 allocates metering and energy-accounting duties among the distribution licensee, STU, the Energy Billing Centre and SLDC, with SLDC finalising accounts and issuing monthly settlement bills (p6–7). A7 and A8 are the pricing core: they itemise the demand, energy and imbalance charges payable by OACs and by OAGs, treat stand-by fixed and usage charges separately, and prescribe the imbalance formulae applied at the drawal or injection point using the UI rate for the block's average frequency. Imbalances are settled at each party's own interface with the licensee and may not be netted off between an OAC and its associated OAG (p7–11).
A9 governs stand-by support: who may take it, the agreement and Commission approval, how stand-by demand is capped, outage-intimation conditions with caps on outage duration and number of events, the licensee's obligation to supply, and a penalty on the licensee for failure (p12–13). A10–A12 cross-refer reactive energy charges and loss levels to the Open Access Regulations and set how planned and unplanned outages of the STU/licensee network are treated (p13–14). A13–A16 cover metering and communication requirements by voltage level, SLDC real-time monitoring, surcharge and additional surcharge, and dispute resolution first by SLDC and then by the Commission (p14–16). A17–A19 give the Commission powers to remove difficulties, to amend, and savings clauses (p16).
Read with this
Amendments and corrections
- Dated 28 Sep 2016Changes some provisions: Terms and Conditions for Intra-State Open Access Regulations, 2016
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.