Skip to content

CERC · Central Electricity Regulatory Commission

Furnishing of Technical Details by Generating Companies Regulations, 2009 — Statement of Reasons

Central Electricity Regulatory Commission (Furnishing of Technical Details by the Generating Companies) Regulations, 2009.

Statement of reasonsDated 14 Oct 2009No. L-7/138/153/2008-CERC dated 14th October 2009

The commission's reasons for the Furnishing of Technical Details by the Generating Companies Regulations, 2009.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cercind.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is CERC's Statement of Reasons disposing of the consultation on the draft CERC (Furnishing of Technical Details by the Generating Companies) Regulations, 2008, and it annexes the revised technical reporting forms that are to be notified with the final regulations (p1–2).

The Commission records that the only stakeholder response came from NTPC Ltd, which asked that a generating company that has already filed its station details be required to re-file in later years only if the station's status changes (p1–2). The Commission rejects this, holding that the value of comprehensive, self-contained annual reports outweighs the saving in filing effort (p2).

On further consideration the Commission adds a substantive requirement: certain additional technical details on operating parameters and conditions are to be called for, using revised forms annexed to the order, and the regulations are to be finalised and notified in the Official Gazette, coming into force from the date of publication (p2). The Gazette date is not printed.

The annexures carry the operative content. Form-A (p3–5) specifies the fields for coal/lignite-fired thermal stations; Form-B (p7–9) for gas, liquid-fuel and diesel stations; Form-C (p10–12) for hydro stations. Each form sets out the items a generating company must report under Section 10(3) of the Electricity Act, 2003 — capacity and configuration, commissioning dates, tied-up beneficiaries and their shares, associated transmission, equipment manufacturers, fuel and its calorific value, design steam/gas parameters, reference conditions, guaranteed heat rates and efficiencies — together with notes on defined terms and electronic filing.

Standard name
Compliance Audit and Furnishing of Information
Primary topics
Compliance and reporting

Read with this

Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cercind.gov.in ↗

Report an issue with this document