CERC · Central Electricity Regulatory Commission
Explanatory Memorandum to Draft Transmission Licence Regulations, 2023
Explanatory Memorandum
Explanatory memorandum to a draftDated 24 Nov 2023No. L-1/270/2023/CERC dated 24.11.2023
Draft
Voltaic holds no final regulation made from this draft.
Explanatory memorandum to the Transmission Licence (Procedure, Terms and Conditions) Regulations, 2023 — Draft.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is CERC's Explanatory Memorandum, dated 24.11.2023 (No. L-1/270/2023/CERC), issued with the draft CERC (Procedure, Terms and Conditions for grant of Transmission Licence and other related matters) Regulations, 2023. It is a consultation-stage document: it explains why the 2009 Transmission Licence Regulations are being replaced and what the draft would change, rather than laying down operative provisions itself.
The Background (pp1–3) records the 2009 Regulations (notified 26.05.2009, amended 26.05.2010) and the developments since: the Ministry of Power's 2021 guidelines for competitive development of transmission and revised standard bidding documents (National Committee on Transmission replacing the Empowered Committee; Transmission Service Agreement now signed with CTUIL), CERC's GNA Regulations 2022 enabling bulk consumers to seek ISTS connection, petitions from bulk consumers wanting dedicated connecting lines, and the need to modify competitively bid projects when CTU transmission plans change. It then describes current licensing practice — licences granted SPV by SPV under TBCB, and separate licences or licence amendments for elements awarded under RTM (pp2–3).
The Proposal (pp3–4) sets out what the draft regulations would do: formalise the grant and amendment of licences for RTM projects; allow a fresh licence for a TBCB win while permitting an existing licensee to amend its licence where projects are bid on a project basis rather than SPV basis; let a bulk consumer build its connecting line through an existing transmission licensee or take its own licence, under a shortened process; and drop Regulation 6(c) of the 2009 Regulations so that dedicated generating-station lines cannot be licensed. Procedural changes include a single hearing in normal cases instead of two, with hearings reserved where the proposal is unclear, a serious objection is raised or rejection is contemplated, and communications moved to digital mode. The memorandum states the 2009 Regulations are proposed to be repealed (p4).
Read with this
Voltaic holds no final regulation made from this draft.
Proposed changes (drafts with no final yet)
- Dated 28 Nov 2023Transmission Licence (Procedure, Terms and Conditions) Regulations, 2023 — Draft
- Dated 28 Nov 2023Public notice: Draft Transmission Licence Grant Regulations, 2023 — Public Notice
- Dated 19 Dec 2023Notice extending the date for comments: Draft Transmission Licence Regulations, 2023 — Extension of comment deadline to 26.12.2023 — Public Notice
- Dated 27 Dec 2023Hearing notice: Public hearing notice — Draft Transmission Licence Regulations, 2023
2 more documents belong here and are not on Voltaic: 2 drafts or notices on a draft not held as English text.
Voltaic last read CERC's website for final documents on 24 Nov 2026 and for drafts on 19 Nov 2026. A document CERC issued after the page that lists it was read may not be held by Voltaic yet.