Summary written by software. Check the regulator's original before you rely on it.
This is the first amendment to the PSERC (Punjab State Grid Code) Regulations, 2013, notified by the Punjab State Electricity Regulatory Commission under s.181 read with s.86(1)(h) of the Electricity Act, 2003, and extending to the whole of Punjab (p1). It is a clause-by-clause substitution exercise: 25 numbered clauses, each replacing, inserting or deleting a specific regulation of the Principal Regulations, with no schedules or forms. It comes into force on gazette publication, printed as 7 January 2019 (p1).
The opening clauses rewrite the definitional base. Clause 2 inserts new definitions in Regulation B — Date of Commercial Operation, Deviation, Trial Operation/Trial Run and Pooling Station (with a proviso deeming a discom/STU substation to be the pooling station where a wind or solar generator has no separate one) — and restates the hierarchy for interpreting undefined terms (p1–2). Clause 3 recasts the composition, convener level and meeting frequency of the four standing committees: Transmission Planning, Operation and Co-ordination, Protection Co-ordination and Commercial & Metering (p2).
Clauses 4–8 are the technical heart: they replace the governor-action regulation (5.3.6), the ban on suppressing governor action through load limiters/ATRS and the third-party testing regime (5.3.7), the primary-response and VWO-margin regulation (5.3.8), the limits on sudden unit output or load swings (5.3.9), and the grid frequency band users must target (5.3.14). Applicability is set by unit size and fuel type, and wind, solar and nuclear stations are exempted from the governor provisions pending Commission review (p2–4).
Clauses 9–11 tighten drawal discipline: SLDC, distribution licensees, users and EHV consumers must stay within net drawal schedule, ensure requisite load shedding, and comply with standard instantaneous message formats issued by SLDC for contingencies (p4–5). Clauses 12–13 restate the introduction and objective of the scheduling chapter, now expressly covering wind and solar integration, SLDC's control-area responsibilities, reactive power pricing and the reservation that nothing prejudices SLDC's s.32/s.33 powers (p5–6).
Clause 14 is the largest insertion: a new Regulation 11.2A creating a self-contained code for declaring Commercial Operation of thermal units, hydro (including pumped storage) units, intra-state transmission elements and communication systems, including notice periods, certification duties, de-rating options, repeat trial runs and clearance timelines (p6–10). Clause 15 adds Regulations 11.3.6A–D treating each distribution company as a notional control area, capping inadvertent deviation by reference to the CERC Deviation Settlement Mechanism Regulations, and covering infirm power during testing (p10–11). Clauses 16–25 delete Regulation 11.3.7 and 11.4(xii) outright, and replace provisions on SLDC contingency directions, hydro scheduling (with a worked energy-adjustment illustration), grid disturbance deemed revision, revision of declared capability after forced outage, special dispensation for scheduling wind and solar generation, and rounding conventions for availability and schedules (p11–13).
Read with this
The regulation
- Dated 14 Feb 2013Punjab State Grid Code Regulations, 2013
Amendments and corrections
Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.