CSERC · Chhattisgarh State Electricity Regulatory Commission
Renewable Energy Generation Tariff Regulations, 2022 — First Amendment, 2024
Chhattisgarh State Electricity Regulatory Commission (Terms and conditions for determination of generation tariff and related matters for electricity generated by plants based on renewable energy sources) (First Amendment) Regulations, 2024
AmendmentDated 6 May 2024In force from 1 Apr 2024No. 107/CSERC/2024- dated 6th May 2024
Replaced by Terms and Conditions for Determination of Tariff for Renewable Energy Sources Regulations, 2025
See that regulation for the date it took effect and for anything it keeps in force.
Amends the Renewable Energy Generation Tariff Regulations, 2022.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to the CSERC (Terms and Conditions for Determination of Generation Tariff and Related Matters for Electricity Generated by Plants Based on Renewable Energy Sources) Regulations, 2022. Issued in Raipur on 6 May 2024 under sections 61 and 86 read with section 181 of the Electricity Act 2003, it substitutes two sub-regulations of the Principal Regulations and extends to the whole of Chhattisgarh for renewable energy generating stations in the state (p2–3). It is expressly brought into force from 01-04-2024 (p3), i.e. before its issue date.
The amendment rewrites Regulation 17.1 on working capital. It splits renewable technologies into two groups and specifies the cost components that make up the working capital requirement: operation and maintenance expenses for one month, receivables for 45 days of energy charges based on normative CUF, and maintenance spares as a percentage of O&M for wind, small hydro, solar PV and solar thermal; and fuel costs for four months based on normative PLF, one month's O&M, 45 days of receivables on fixed and variable charges, and maintenance spares for biomass, biogas, non-fossil-fuel cogeneration, municipal solid waste and refuse-derived fuel projects (p3).
The amendment also replaces Regulation 20.1 on late payment surcharge. Where payment is delayed beyond 45 days from billing, the generating company levies a surcharge at the State Bank of India one-year marginal cost of funds based lending rate as on 1 April of the relevant financial year plus five percent, with a proviso for defaults spanning financial years and a step-up for successive months of delay subject to a cap above the base rate (p3).
If your work touches working-capital norms or payment-security terms for Chhattisgarh RE generators, these are the two operative clauses to read. Nothing else in the Principal Regulations is touched, and the document states no repeal or savings provisions.
Read with this
The regulation
- Dated 28 Nov 2022Renewable Energy Generation Tariff Regulations, 2022
2 more documents belong here and are not on Voltaic: 2 copies in another language.
Voltaic last read CSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document CSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.