Chhattisgarh State Electricity Regulatory Commission (Terms and conditions for determination of generation tariff and related matters for electricity generated by plants based on renewable energy sources) (First Amendment) Regulations, 2024

AmendmentDated 6 May 2024In force from 1 Apr 2024No. 107/CSERC/2024- dated 6th May 2024

Replaced by Terms and Conditions for Determination of Tariff for Renewable Energy Sources Regulations, 2025

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Renewable Energy Generation Tariff Regulations, 2022.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on cserc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the First Amendment to the CSERC (Terms and Conditions for Determination of Generation Tariff and Related Matters for Electricity Generated by Plants Based on Renewable Energy Sources) Regulations, 2022. Issued in Raipur on 6 May 2024 under sections 61 and 86 read with section 181 of the Electricity Act 2003, it substitutes two sub-regulations of the Principal Regulations and extends to the whole of Chhattisgarh for renewable energy generating stations in the state (p2–3). It is expressly brought into force from 01-04-2024 (p3), i.e. before its issue date.

The amendment rewrites Regulation 17.1 on working capital. It splits renewable technologies into two groups and specifies the cost components that make up the working capital requirement: operation and maintenance expenses for one month, receivables for 45 days of energy charges based on normative CUF, and maintenance spares as a percentage of O&M for wind, small hydro, solar PV and solar thermal; and fuel costs for four months based on normative PLF, one month's O&M, 45 days of receivables on fixed and variable charges, and maintenance spares for biomass, biogas, non-fossil-fuel cogeneration, municipal solid waste and refuse-derived fuel projects (p3).

The amendment also replaces Regulation 20.1 on late payment surcharge. Where payment is delayed beyond 45 days from billing, the generating company levies a surcharge at the State Bank of India one-year marginal cost of funds based lending rate as on 1 April of the relevant financial year plus five percent, with a proviso for defaults spanning financial years and a step-up for successive months of delay subject to a cap above the base rate (p3).

If your work touches working-capital norms or payment-security terms for Chhattisgarh RE generators, these are the two operative clauses to read. Nothing else in the Principal Regulations is touched, and the document states no repeal or savings provisions.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Return, financing and working capital, Late payment surcharge and rebate, Renewable energy tariff

Read with this

The regulation

2 more documents belong here and are not on Voltaic: 2 copies in another language.

Voltaic last read CSERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document CSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on cserc.gov.in ↗

Report an issue with this document