This is KERC's principal regulation creating a metering, connectivity and tariff framework for rooftop aero turbines (small wind plants on consumers' roofs), either combined with rooftop solar or standalone. Pages 1–2 give the preamble and the Commission's order approving the Regulations: the draft was gazetted on 10.10.2024, a public hearing was held on 06.12.2024, and the Regulations were made on 20.01.2025 under sections 86(1), 181, 61 and 62 of the Electricity Act, 2003, tied to the Karnataka RE Policy 2022-27 initiative on rooftop aero turbines with solar.
The operative text (pp3–16) runs in 13 regulations. Regulation 1 names the Regulations and makes them effective from Gazette publication. Regulation 2 defines the key actors and arrangements — eligible consumer, RAT plant, SRTPV plant, gross metering, net metering, interconnection point, billing period. Regulation 3 requires distribution licensees to offer gross or net metering on a non-discriminatory, first-come-first-served basis. Regulation 4 sets the capacity conditions for installation, including an eligibility ceiling tied to the consumer's sanctioned load and a minimum installed capacity. Regulation 5 lays down the licensee's application, approval, PPA and commissioning procedure, with quarterly reporting to the Commission. Regulation 6 specifies interconnection voltage levels by installed capacity, transformer and line loading limits, applicable technical codes (KERC Grid Code, Distribution Code, CEA distributed-generation, meter and safety regulations) and the consumer's safety, anti-islanding and isolation-switch obligations.
Regulations 7 and 8 deal with tariff: generic tariffs determined each control period on application or suo motu, with revision for major parameter changes, and the parameters used — CUF, a single-part tariff of O&M, depreciation, interest on loan and working capital, and return on equity, tariff period and levelised design, capital cost, debt-equity, depreciation method, RoE, O&M escalation and tax treatment. Regulation 9 covers metering under gross and net arrangements; Regulation 10 covers energy accounting and settlement; Regulation 11 covers PPA formats and when Commission approval is needed. Regulations 12 and 13 provide the grievance route and the Commission's power to remove difficulties, relax provisions and amend the Regulations.
Read with this
Other copies of these documents (1)
- Dated 20 Jan 2025Rooftop Aero Turbine with Solar or Without Solar Regulations, 2025
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.