Draft Order prescribing Renewable Purchase Obligation, FY 2017-18 to FY 2019-20

Draft Order prescribing Renewable Purchase Obligation

Published with a draftDated 1 Feb 2019

Draft

Voltaic holds no final regulation made from this draft.

Published with the draft RPO and REC Framework Implementation Regulations, 2018.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on derc.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page draft order of the Delhi Electricity Regulatory Commission fixing renewable purchase obligation (RPO) targets for obligated entities other than distribution licensees, issued under Regulation 4 of the DERC (RPO and REC Framework Implementation) Regulations, 2018 (p1).

Clause 1 makes the order applicable only to two categories of obligated entity: captive users as defined in regulation 2(5) of the RPO-REC Regulations, and open access consumers as defined in regulation 2(16) (p1).

Clause 2 sets out how the annual target is to be computed for FY 2017-18 to FY 2019-20 — as a percentage of the entity's total consumption, with power procured through hydro electric plants excluded from that consumption base. A proviso requires the solar component of the obligation to be met only from solar-based generation (p1).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.