KERC · Karnataka Electricity Regulatory Commission
Forecasting, Scheduling and Deviation Settlement Mechanism for Sellers of Wind, Solar and WS-Hybrid Generation Sources Regulations, 2026
Karnataka Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement Mechanism and related matters for Sellers of Wind, Solar and WS-Hybrid Generation sources) Regulations, 2026.
RegulationDated 19 Jun 2026Published in the Gazette 22 Jun 2026KERC/WS(DSM) /2026-27/2150 dated 19.06.2026
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is KERC's June 2026 principal regulation for forecasting, scheduling and deviation settlement for sellers from wind, solar and wind-solar hybrid generation sources in Karnataka. It opens with a preamble and statement of reasons (pp1–11) explaining why the Commission is replacing its 2015 wind/solar DSM framework and aligning scheduling with KEGC 2025 and IEGC 2023. The Commission records the public consultation on the 2025 draft (p3), the public hearing on 07.04.2025 (p3), and its decisions on stakeholder objections: refusing exemptions for feeder-level solarisation/PM KUSUM and sub-5 MW solar (p3, p7); moving wind/solar schedule revisions to the 7th/8th time block in line with KEGC 2025 (pp3–5); adopting scheduled generation as the DSM denominator and annual capping of deviation charges (p5); excluding buyers from DSM (p6); tightening the solar tolerance band (pp6–7); allowing generator-end metering for STOA inter-State sales where no separate feeder exists (pp7–9); applying CERC DSM 2024 to inter-State sales (p9); and adopting a deemed schedule for zero scheduled generation (pp9–10).
Regulations 1–4 (pp11–14) name the regulations, bring them into force from Gazette publication, define terms and set applicability by contracted capacity at the pooling station/interface point: wind 10 MW and above, solar and wind-solar hybrid 5 MW and above, with a note on ESS capacity. Regulations 5–12 (pp14–18) allocate duties to SLDC and intra-State entities under KEGC 2025; detail QCA roles, registration and the option to use SLDC forecasting; prescribe week-ahead, day-ahead and intra-day forecasts, aggregation of pooling stations, and scheduling revision as per KEGC 2025; give renewable generation dispatch priority; and set metering, telemetry, communication and technical-standard obligations.
Regulations 13–15 (pp19–23) are the core DSM framework: error computation and treatment of zero schedules; monthly State Deviation Pool Account settlement; mandatory data provision; tolerance bands for wind, solar, hybrid and ESS; payment for actual intra-State energy; deviation charge tables for wind/hybrid and solar sales within Karnataka; the annual cap and its three-year review; inter-State sale treatment under CERC DSM 2024 and STOA accounting via generator-end meters; monthly publication of pool account details; curtailment information and exemptions; and payment timelines with interest for delay.
Regulations 16–24 (pp23–25) cover revocation of registration and encashment of bank guarantee/revolving LC, utilisation of deviation funds, power to relax and amend, repeal of the 2015 regulations with savings, removal of difficulties, final interpretation by the Commission, gaming proceedings and disallowance of deviation charges, and suo motu orders. Page 25 also carries an unrelated Government of Karnataka Lokayukta notification.
Read with this
Earlier drafts
Voltaic last read KERC's website for final documents on 24 Nov 2026 (3 pages) and for drafts on 23 Nov 2026. A document KERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of KERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.