Skip to content

UPERC · Uttar Pradesh Electricity Regulatory Commission

SLDC Fee and Charges Regulations, 2004

Uttar Pradesh Electricity Regulatory Commission (Procedure, Terms & Conditions for payment of Fee and Charges to State Load Despatch Centre and other related provisions) Regulations, 2004

RegulationDated 7 Jun 2005UPERC/Secy/Regulation/05-250 dated 7 June, 2005

Replaced by SLDC Fees and Charges Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on uperc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is UPERC's principal regulation on how the State Load Despatch Centre (SLDC) is to be paid for its despatch and system-operation work, and on the duties SLDC must discharge in return. It is issued as Notification No. UPERC/Secy/Regulation/05-250, Lucknow, dated 7 June 2005, made under s.32 read with s.181 of the Electricity Act 2003 (p11). The text appears in two language versions — Hindi on pp2–10 and English on pp11–24 — and reg 19 (p24) says the English version prevails in case of dispute.

Regulations 1–2 (p11–15) give the short title, scope and commencement, and a definitions list covering the Act, SLDC, STU, grid code, wheeling, captive generating plant, deemed licensee, and inter-State and intra-State transmission. Regulation 1(b) confines application to generating companies (including captive, co-generating and renewable generation) and licensees connected with the UP power system.

Regulations 3–7 (p15–17) constitute the SLDC — to be operated by a Government company or, until the State Government notifies otherwise, by the STU — list its functions (scheduling and despatch, real-time control, supervision of the intra-State transmission system, grid monitoring, energy accounting), its obligations towards the RLDC, ABT and Open Access rules, and its duties, including framing a scheduling procedure and an energy-account/UI-account scheme within one month of publication and preparing UI bills. It is barred from trading in electricity.

Regulations 8–14 (p18–22) are the money part: fee slabs payable by generating stations and captive plants keyed to agreement tenure; fixed monthly charges payable by intra-State transmission licensees built up from return on equity, depreciation, interest, O&M, working capital and taxes; the cost-determination principles, normative debt-equity and depreciation limits; mode of payment and treatment of fee receipts; billing, due date and late-payment surcharge; SLDC accounting and financial-year rules; and the annual revenue requirement procedure with its filing deadline and public hearing before the Commission. Regulations 15–19 (p22–24) cover penalties for non-compliance with SLDC directions, dispute adjudication by the Commission, the Commission's power to amend or depart from its own regulations, removal of difficulties and the language clause.

Standard name
SLDC Fees and Charges
Primary topics
SLDC and RLDC fees and charges, ARR and true-up, Return, financing and working capital

Read with this

No other documents to read with it are on Voltaic.

Voltaic last read UPERC's website for final documents on 24 Nov 2026 (2 pages). A document UPERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on uperc.org ↗

Report an issue with this document