Summary written by software. Check the regulator's original before you rely on it.
This is UPERC's principal regulation on how the State Load Despatch Centre (SLDC) is to be paid for its despatch and system-operation work, and on the duties SLDC must discharge in return. It is issued as Notification No. UPERC/Secy/Regulation/05-250, Lucknow, dated 7 June 2005, made under s.32 read with s.181 of the Electricity Act 2003 (p11). The text appears in two language versions — Hindi on pp2–10 and English on pp11–24 — and reg 19 (p24) says the English version prevails in case of dispute.
Regulations 1–2 (p11–15) give the short title, scope and commencement, and a definitions list covering the Act, SLDC, STU, grid code, wheeling, captive generating plant, deemed licensee, and inter-State and intra-State transmission. Regulation 1(b) confines application to generating companies (including captive, co-generating and renewable generation) and licensees connected with the UP power system.
Regulations 3–7 (p15–17) constitute the SLDC — to be operated by a Government company or, until the State Government notifies otherwise, by the STU — list its functions (scheduling and despatch, real-time control, supervision of the intra-State transmission system, grid monitoring, energy accounting), its obligations towards the RLDC, ABT and Open Access rules, and its duties, including framing a scheduling procedure and an energy-account/UI-account scheme within one month of publication and preparing UI bills. It is barred from trading in electricity.
Regulations 8–14 (p18–22) are the money part: fee slabs payable by generating stations and captive plants keyed to agreement tenure; fixed monthly charges payable by intra-State transmission licensees built up from return on equity, depreciation, interest, O&M, working capital and taxes; the cost-determination principles, normative debt-equity and depreciation limits; mode of payment and treatment of fee receipts; billing, due date and late-payment surcharge; SLDC accounting and financial-year rules; and the annual revenue requirement procedure with its filing deadline and public hearing before the Commission. Regulations 15–19 (p22–24) cover penalties for non-compliance with SLDC directions, dispute adjudication by the Commission, the Commission's power to amend or depart from its own regulations, removal of difficulties and the language clause.
Read with this
No other documents to read with it are on Voltaic.
Voltaic last read UPERC's website for final documents on 24 Nov 2026 (2 pages). A document UPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.