DERC · Delhi Electricity Regulatory Commission
Power System Development Fund Regulations, 2019
Delhi Electricity Regulatory Commission (Power System Development Fund) Regulations, 2019
RegulationDated 27 Dec 2019F.3(551)/Tariff-Engg./DERC/2018-19/6195 dated 27/12/2019
Summary
Summary written by software. Check the regulator's original before you rely on it.
DERC's Power System Development Fund Regulations, 2019 create and govern a dedicated Delhi fund (PSDF) built mainly out of Deviation Settlement Charges, and set up the machinery for spending it on intra-state grid strengthening (p1–3). The notification is dated 27/12/2019 and takes effect from publication in the Official Gazette; no Gazette date is printed (p1).
Regulation 3 constitutes the fund, routes the balance of the State Deviation Pool Account and other Commission-notified charges into it on a monthly basis, and makes Delhi SLDC the fund's custodian; un-transferred accumulations are to be moved into PSDF (p2–3). Regulation 4 lists the eligible purposes — strategic transmission schemes flagged by SLDC, reactive compensation and voltage support, protection schemes, R&M of transmission, and allied work such as PMUs, SLDC upgrades, smart grid, storage and DSM — and sets the priority order for ranking schemes; distribution utility proposals are allowed only if incidental to intra-state transmission or grid safety and not already covered by another GoNCTD scheme (p3).
Regulation 5 designates SLDC as Nodal Agency and lists its secretariat, procedure-drafting, accounting and reporting duties. Regulations 6 and 7 create the Appraisal Committee (chaired by Secretary, Department of Power) for techno-economic scrutiny and prioritisation, and the Monitoring Committee (chaired by a Commission Member) for sanction, release and supervision (p4–5). Regulation 8 lays out the application-to-sanction pipeline through the Nodal Agency, Appraisal Committee, Commission and Monitoring Committee, and requires utilities to keep a separate PSDF account head (p5–6).
Regulation 9 makes PSDF support a grant whose size depends on strategic importance and project size, with detailed guidelines left to the Monitoring Committee (p6). Regulations 10–13 cover execution and O&M (under the DERC Tariff Regulations, 2017), budget/accounts/audit via a Detailed Procedure, implementing agencies and outcome-based monitoring, and an annual report to be laid before the Legislative Assembly (p6–7). Regulations 14–19 are standard enabling clauses: removal of difficulties, relaxation, interpretation, inherent powers, enquiry procedure under the DERC Conduct of Business Regulations, 2001, and amendment power (p7).
Read with this
Earlier drafts
- Dated 11 Jan 2019Power System Development Fund Regulations, 2019
Voltaic last read DERC's website for final documents on 24 Nov 2026 and for drafts on 23 Nov 2026. A document DERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of DERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.