Skip to content

JSERC · Jharkhand State Electricity Regulatory Commission

Determination of Tariff for Procurement of Power from Wind, Biogas, MSW and RDF-based Projects Regulations, 2016 — First Amendment, 2020

Jharkhand State Electricity Regulatory Commission (Determination of Tariff for Procurement of Power from Wind, Biogas, Municipal Solid waste and Refuse Derived fuel-based Power Projects) (First Amendment) Regulations, 2020

AmendmentDated 31 Dec 2020Published in the Gazette 21 Jan 2021No.82- dated 31st December, 2020

Amends the Determination of Tariff for Procurement of Power from Wind, Biogas, Municipal Solid Waste and Refuse Derived Fuel based Power Projects Regulations, 2016.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on jserc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is JSERC's First Amendment to its 2016 regulations for determining tariffs for power procured from wind, biogas, municipal solid waste and refuse-derived-fuel based projects (p1). It was issued on 31 December 2020 and printed in the Jharkhand Gazette Extraordinary of 21 January 2021 (p1).

It does two things. First, it extends the control period of the Principal Regulations — the Commission's stated reason being technology advancement in the wind sector and tariffs discovered through competitive bidding (p1). Second, it amends Regulation 4 of the Principal Regulations by adding a proviso to Regulation 4.58, allowing the Commission to modify the parameters set there after a prudence check, on a case-to-case basis (p2).

Clause 1 carries the short title and commencement: the amendment takes effect from the date of Gazette publication — 21 January 2021 — unless reviewed earlier or extended by the Commission, and remains in force up to 31 March 2025 (p1–2). Clause 2 is the operative amendment (p2).

Practical upshot: developers and procurers of wind, biogas, MSW and RDF projects in Jharkhand get a longer tariff control period, but the Commission keeps case-by-case discretion over the Regulation 4 parameters. The text does not itself print the extended control-period dates, nor list the parameters in Regulation 4.58.

Standard name
Renewable Energy Tariff Regulations
Primary topics
Renewable energy tariff, Tariff determination, Multi Year Tariff (MYT)

Read with this

Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on jserc.org ↗

Report an issue with this document