BERC · Bihar Electricity Regulatory Commission
Terms and Conditions for Determination of Tariff Regulations, 2007 — 2nd Amendment, 2014
Bihar Electricity Regulatory Commission (Terms and Conditions for Determination of Tariff) (2 Amendment) Regulations, 2014
AmendmentDated 26 Mar 2014Published in the Gazette 27 Mar 2014BERC-Case-No.- 181 dated The 26th March 2014
Replaced by Multi Year Distribution Tariff Regulations, 2021
See that regulation for the date it took effect and for anything it keeps in force.
Amends a regulation Voltaic does not hold.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the Bihar Electricity Regulatory Commission's second amendment to its tariff-determination regulations, issued by order of the Commission and published in the Bihar Gazette (Extraordinary) on 27 March 2014; the notification itself is dated 26 March 2014 (p1). It extends to the whole of Bihar and comes into force on Gazette publication (p1).
The operative part is three changes to Regulation 73 of the principal tariff regulations (p1–2). First, the return-on-equity clause is substituted: equity return is computed on the equity base determined under Regulation 71, at 15.5% for projects commissioned on and after 01.04.2015, with an additional 0.5% margin for projects completed and commercially operated within the schedule in Appendix-C(1); where a project misses that schedule, the extra cost of the delay is to be borne by the petitioner and not passed through in tariff (p1–2). Second, a clause is added to Regulation 73(3)(b) allowing reimbursement of application fee, publication expenses and annual licence fee, after prudence check, at the time of tariff determination (p2). Third, the interest-on-working-capital clause is substituted so that the rate is a fixed spread over the base rate, payable on a normative basis even if the licensee has taken no outside working-capital loan or has taken it at different rates (p2).
Appendix C(i), printed with the notification, is the time schedule — in months, by voltage class and terrain — within which transmission lines, substations and HVDC terminals must be completed; it is the benchmark against which the timely-completion incentive is judged (p2).
Read with this
Voltaic does not hold the regulation itself.
Amendments and corrections
Voltaic last read BERC's website for final documents on 24 Nov 2026 and for drafts on 21 Nov 2026. A document BERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.