RERC · Rajasthan Electricity Regulatory Commission
Transmission Licensee's Standards of Performance Regulations, 2004
Rajasthan Electricity Regulatory Commission (Transmission Licensee's Standards of Performance) Regulations, 2004
StandardsDated 20 Apr 2004No. Secy / RERC/REG/ 24 - dated 20th April 2004
Replaced by Standards of Performance of Transmission Licensee Regulations, 2021
See that regulation for the date it took effect and for anything it keeps in force.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action already taken under the repealed regulations shall be deemed to have been done or taken under these Regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
RERC issued these regulations on 20 April 2004 under s.57 read with ss.9, 33 and 34 of the Rajasthan Power Sector Reforms Act 1999, after consulting its Advisory Committee and other stakeholders (p1). They bind all transmission licensees — in practice RVPN — and fix the operational performance the licensee must deliver on the State Transmission System, with matching obligations on distribution licensees, RVUN and other users at interconnection points.
Regulations 1–3 give the title, application to all transmission licensees, commencement on Gazette publication, definitions, and the objective: minimum grid performance, a basis for users to design their equipment against the electrical environment, and progressive movement from national towards international standards (p1–2).
Regulation 4 is the spine of the document: standards are implemented in three stages — a one-year Preliminary Stage (Level 1), a Transition Stage of up to two years with investment (Level 2), and a Final Stage thereafter (Level 3) (p2). Most later standards are graded against these levels, and a few apply only in the Final Stage.
Regulation 5 sets system availability obligations, with a formula for hourly substation availability, exclusions for outages caused by SLDC emergency instructions, connection-condition breaches or distribution system faults, and a capacity-weighted aggregation across substations serving a distribution licensee (p2–3). Regulation 6 covers voltage: a voltage profile band for each nominal voltage at EHV substations monitored at SLDC, phase voltage unbalance limits (Final Stage only), the Voltage Variation Index formula and annual limits determined by RVPN, and a current unbalance limit with a 12-hour remedy window and referral to the Grid Code committee (p3–4). Regulation 7 covers frequency — operation as part of the Northern Grid, IEGC compliance, target and statutory frequency bands, and a Frequency Variation Index to be adopted as and when IEGC stipulations are implemented in the Northern Region (p4–5).
Regulation 8 treats reliability in three senses: system adequacy measured by loss of load expectation, n-1 security tested against a stepped import increase, and service reliability measured by SAIFI and SAIDI at EHV grid substations, excluding natural events, scheduled outages, load shedding and PGCIL/BBMB failures (p5–7). Regulation 9 sets harmonic distortion measurement and control, naming measurement standards, monitoring intervals, advance notice to RVUN and distribution licensees, and a register of harmonic-prone metering points (p7–8). Regulation 10 requires I.E. Rules safety compliance, designated control persons under the Grid Code, a licensee Safety Manual effective from the preliminary stage, and an Annual Review Committee reporting to the Commission (p8–9).
Read with this
Amendments and corrections
Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.