RERC · Rajasthan Electricity Regulatory Commission

Transmission Licensee's Standards of Performance (Second Amendment) Regulations, 2016

Rajasthan Electricity Regulatory Commission (Transmission Licensee's Standards of Performance) (Second Amendment) Regulations, 2016

AmendmentDated 19 Jan 2016No. RERC/Reg. No. 114 dated 19 January 2016

Replaced by Standards of Performance of Transmission Licensee Regulations, 2021

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Transmission Licensee's Standards of Performance Regulations, 2004.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or any action already taken under the repealed regulations shall be deemed to have been done or taken under these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on rerc.rajasthan.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A one-page RERC notification dated 19 January 2016 (p1) that amends the Commission's Transmission Licensee's Standards of Performance Regulations for a second time. Regulation 1 gives the short title, states that the regulations apply to all transmission licensees, and brings them into force on publication in the official gazette — the gazette date itself is not printed. Regulation 2 substitutes sub-regulation (1), "Voltage Profile", of Regulation 6, obliging the licensee to make all possible efforts to hold grid voltage within specified maximum and minimum bands at all EHV substations of its transmission system and, on a real-time basis, at SLDC, with the bands set out in a table keyed to nominal system voltages from 765 kV down to 11 kV (p1). Issued by order of the Commission, signed by Secretary G. K. Sharma.

Standard name
Standards of Performance
Primary topics
Power quality, Standards of performance

Read with this

Amendments and corrections

Voltaic last read RERC's website for final documents on 24 Nov 2026. A document RERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on rerc.rajasthan.gov.in ↗

Report an issue with this document