MPERC · Madhya Pradesh Electricity Regulatory Commission
Conventional Fuel based Captive Power Plants (Power Purchase and Other Matters) Regulations, 2009 — Revision-I
Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel based Captive Power Plants) Regulations, (Revision-I) 2009 {RG-30 (I) of 2009}
RegulationDated 31 Jan 2009No. 254-MPERC-2009 dated 31st January, 2009
2 amendments to it are on Voltaic, the latest dated 20 Feb 2024.
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is MPERC's first revision of its 2006 regulations on captive power plants burning conventional (fossil) fuels. The Commission states it revised the 2006 Regulations — notified 29.9.2006 as G-30 of 2006 — to harness surplus generation capacity of captive units and cut peak-time shortages, and to align the rules with the Ministry of Power's Tariff Policy of 6 January 2006 (p1). The regulations extend to the whole of Madhya Pradesh, apply only to conventional-fuel CPPs, and come into force on gazette publication; the gazette date is not printed (p1).
Chapter I (p1–4) carries the short title and commencement, defines the working vocabulary — firm and in-firm power, CPP holder, captive user, stand-by support, licensee (a distribution licensee), State Transmission Utility — and reproduces the Electricity Rules 2005 test for who counts as a captive plant, together with what follows if the annual captive-use test is missed (the year's consumption is treated as generating-company supply and charged as open access) (p3).
Chapter II (p4–5) sets the grid and technical conditions: compliance with the MP Electricity Grid Code and the Indian Electricity Grid Code, SLDC supervision at 132 kV and Distribution Licensee Control Centre supervision at 33/11 kV, disputes referred to the Commission, valid statutory clearances, and who bears the cost of interconnection assets.
Chapter III (p5–7) governs sale of surplus CPP power to the distribution licensee: a rate ceiling set by the Commission's tariff orders with a competitive-bidding option under Ministry of Power guidelines, contracting through M.P. Power Trading Co. Ltd., time-of-day differentiation of firm-power rates, a discounted rate for in-firm power, 15-minute scheduling, measurement at the interface point, a step-wise settlement methodology, no deemed generation, and payment, rebate and penal-interest terms.
Chapter IV (p8–13) creates the stand-by support regime — eligibility at a minimum capacity, a table classifying five transaction types, separate conditions and charges for Parts A, B and C that are allowed the facility, commitment charges, fixed and energy charges on the temporary-supply tariff, double-billing of excess demand, power-factor treatment, a penalty on the licensee for failure to supply, force majeure, and metering/invoicing duties; it closes with power to remove difficulties, power to amend and savings clauses (p12–13). An annexure (p14–15) works a commitment-charge example for an EHT consumer.
Read with this
Amendments and corrections
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of MPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.