Conventional Fuel Based Captive Power Plants Regulations, 2009 — First Amendment, 2023
Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel based Captive Power Plants) Regulations, (Revision-I) 2009 (First Amendment) {RG-30 (I) (i) of 2023}
AmendmentDated 7 Dec 2023No. MPERC/2023/2740 dated 7th December 2023
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is the First Amendment to MPERC's 2009 regulations on power purchase and other matters for conventional-fuel captive power plants, issued at Bhopal on 7 December 2023 (p1). It is a short four-page instrument whose stated purpose is to align the state's captive-plant rules with the Electricity Amendment Rules 2023 issued by the Ministry of Power on 30 June and 1 September 2023 (p1). It extends to the whole of Madhya Pradesh and applies only to captive power plants using conventional fuels (p1). It comes into force on the date of publication in the official gazette of the Government of Madhya Pradesh; that gazette date is not printed in the text (p1).
Regulation 1 carries the short title, extent and commencement (p1). Regulation 2 does the amending. Regulation 2.1 inserts three new definitions into regulation 1.4 of the Principal Regulations — Affiliate Company, Designated Authority and Subsidiary Company — the latter two by cross-reference to other instruments (p2). Regulation 2.2 substitutes the test for identifying a plant as a captive power plant, restating the conditions in clause 3(1)(a) and (b) of the Electricity Rules, 2005 as amended, including the ownership and consumption thresholds, the affiliate-company proviso, and the treatment of cooperative societies, associations of persons and SPV generating stations (p2–3). Regulation 2.3 substitutes regulation 1.6, setting out the consequence of failing the annual captive-use test — the whole of the electricity consumed is treated as a generating company supply and attracts open access charges — and routing disputes over captive status to the redressal mechanism in MPERC's 2023 verification regulations (p3–4). It also clarifies that captive consumption may be direct or through an energy storage system, and that consumption by a subsidiary company counts as captive consumption (p4).
Read with this
The regulation
Amendments and corrections
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.