Power Purchase and Other Matters with respect to Conventional Fuel Based Captive Power Plants Regulations, 2009 — Second Amendment, 2024

Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel based Captive Power Plants) Regulations, (Revision-I) 2009 (Second Amendment) {ARG-30 (I) (ii) of 2024}

AmendmentDated 20 Feb 2024MPERC/2024/480 dated 20th February 2024

Amends the Conventional Fuel based Captive Power Plants (Power Purchase and Other Matters) Regulations, 2009 — Revision-I.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on mperc.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is the Second Amendment to MPERC's 2009 regulations on power purchase and other matters for conventional-fuel captive power plants in Madhya Pradesh, issued in Bhopal on 20 February 2024 (p1). It is a short, targeted instrument: the Commission states that changes are needed to align the 2009 Regulations with the Electricity Amendment Rules 2023 notified by the Ministry of Power on 01.09.2023, and to revise the charges for standby support (p1).

Regulation 2 re-anchors how captive status is determined (p1–2). Sub-clause (aa) of Regulation 1.4 of the Principal Regulations is deleted; Regulation 1.5 is replaced so that a plant is identified as a captive power plant only if it satisfies the conditions in the Electricity Rules, 2005 as amended from time to time; and Regulation 1.6 is replaced so that failure to satisfy those conditions in a financial year carries the consequences set out in Regulation 7 of the MPERC (Verification of Captive Generation Plants and Captive Users) Regulations, 2023, with the generator and captive user(s) entitled to represent against the designated authority's determination under Regulation 9 of those 2023 Regulations (p2).

Regulation 3 amends Regulation 4.15 of the Principal Regulations, revising the commitment charges: the sums "Rs. 31" and "Rs. 25" are substituted by "Rs. 16" and "Rs. 13" respectively (p2). The second proviso to that clause is replaced so that the commitment charges extended by order dated 14.12.2023 apply only up to the commencement of this amendment, while the revised charges apply till 31.03.2027 and are to be reviewed thereafter (p2).

Commencement is on publication in the Madhya Pradesh official gazette (p1); the gazette date is not printed in this text.

Standard name
Captive Generation Regulations
Primary topics
Captive status, Open access charges

Read with this

3 more documents belong here and are not on Voltaic: 3 copies in another language.

Voltaic last read MPERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (4 pages). A document MPERC issued after the page that lists it was read may not be held by Voltaic yet.