Summary
Summary written by software. Check the regulator's original before you rely on it.
The Jharkhand State Electricity Regulatory Commission (Open Access in Intra-State Transmission & Distribution) Regulations, 2005, notified as No. JSERC/Regulation/199 dated 27/06/2005 and published in the Jharkhand Gazette Extraordinary on 28 June 2005, create the framework for open access use of intra-state transmission and distribution systems in Jharkhand (p1). They are made under s.181 read with s.42(2) of the Electricity Act, 2003, apply to the whole State, and commence from gazette publication, except Regulation 6(iii), which starts after 90 days, with interim short-term reservations on a first-come-first-served basis (p1).
Regulations 2–4 define key terms and divide customers into long-term (10 years or more, with existing consumers/beneficiaries deemed long-term) and short-term (up to one year) categories, and say open access customers must comply with the Grid Code and are treated as consumers for the Electricity Supply Code and standards of performance (pp2–4). Regulations 5–15 set out how access is granted: long-term applications to STU/transmission licensee/distribution licensee (with SLDC copy), short-term applications to SLDC, nodal agency roles, application contents and fees, system studies and capacity relinquishment/transfer; they also bar transfer of short-term reserved capacity and provide for surrender and reduction (pp4–8).
Regulations 16–23 prescribe charges: annual transmission/distribution charges shared by long-term customers after adjusting short-term revenue; a formula-based short-term rate; 50:50 allocation of short-term revenue; scheduling and system operation charges; cross-subsidy and additional surcharges (the latter capped at two years); UI charges (cross-referring the 2010 Balancing & Settlement Regulations); and reactive energy charges (pp8–12).
Regulations 24–31 address processing timelines, curtailment priority, standard commercial conditions, special energy meters, and energy losses, including a network-loss scenario table for open access settlement (pp12–14). Regulations 32–41 cover Grid Code compliance, collection/disbursement, phased opening of open access by capacity thresholds and dates, website disclosure, redressal, coordination, metering, and difficulty removal (pp15–19). The text carries asterisked 2010 amendments (Gazette Notification No. 42 dated 28/01/2010) in the UI, reactive energy and loss clauses, so it is a consolidated working text rather than the untouched 2005 instrument (pp11–13).
Read with this
Amendments and corrections
Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.