JSERC · Jharkhand State Electricity Regulatory Commission

Open Access in Intra-State Transmission and Distribution, 2005 — First Amendment Regulations, 2010

Jharkhand State Electricity Regulatory Commission (Open Access in Intra-State Transmission and Distribution-First Amendment) Regulations, 2010

AmendmentDated 27 Jan 2010Published in the Gazette 28 Jan 2010No.25 dated The 27th January, 2010

Replaced by Terms and Conditions for Intra-State Open Access Regulations, 2016

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Open Access in Intra-State Transmission & Distribution Regulations, 2005.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on jserc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

The Jharkhand State Electricity Regulatory Commission's first amendment to its 2005 open access regulations, notified 27 January 2010 and published in the gazette on 28 January 2010 (p1), reworks four clauses of the parent regulation. It extends to the whole of Jharkhand and takes effect from gazette publication (p1).

Page 2 replaces the definition of "open access customer" so that it expressly covers both an Open Access Consumer and an Open Access Generator — including a generating company, a captive generating plant or a licensee availing or intending to avail open access — and adds a definition of VAR (reactive power).

Page 3 redirects settlement of the mismatch between scheduled and actual drawal and injection to the pricing mechanism of the JSERC (Balancing & Settlement Mechanism for Open Access) Regulations, 2010, Chapters A8 and A9, rather than dealing with it in the open access regulation itself. The same page substitutes clause 21 wholesale: OACs and OAGs must provide VAR compensation so that no reactive power is drawn from or injected into the network, with a four-way pay/receive regime keyed to the interface voltage band, priced per kVARh with effect from 1 April 2010, escalating annually and revisable by Commission order.

Pages 4–5 add network-loss provisions to clause 31: formulas to convert an OAG's injection schedule into an OAC's drawal schedule and vice versa using applicable network losses, plus a table of loss levels and charges keyed to the Discom location and voltage at each end of the transaction. Those values are to be read from the Commission's latest tariff orders, and loss levels for non-conventional sources are left to the Commission to decide from time to time.

Standard name
Open Access Regulations
Primary topics
Open access, Losses and loss reduction, Power quality

Read with this

Voltaic last read JSERC's website for final documents on 24 Nov 2026 (5 pages) and for drafts on 21 Nov 2026. A document JSERC issued after the page that lists it was read may not be held by Voltaic yet.