Grid Connectivity and Intra-State Open Access Regulations, 2011 — Draft

Tamil Nadu Electricity Regulatory Commission (Grid connectivity and Intra-State Open Access) Regulations, 2011.

Draft regulationDated 2 Jun 2011TNERC/ISOA/…………… dated 02-06-2011

Draft

A proposal, not law. Voltaic holds no final regulation made from this draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft TNERC regulation, dated 2 June 2011 and open for comments until 1 July 2011, that would replace the 2005 intra-State open access regulations and establish a single framework for grid connectivity and open access in Tamil Nadu (p1, p51). It is made under section 181 of the Electricity Act, 2003 and would commence on publication in the Government Gazette, a date not printed in the document (p1).

Chapter 1 gives the title, scope and definitions, including the duration categories for long-, medium- and short-term open access (p1–5). Its scope covers use of intra-State transmission and/or distribution systems, including conjoint use with inter-State systems, subject to SLDC directions and Commission-approved restriction and control measures (p1–2). Chapter 2 deals with connectivity. Applicants at 10 MW and above or 66 kV and above connect to the intra-State transmission system, while smaller or lower-voltage applicants connect to distribution (p5). It prescribes application forms and fees, STU or distribution licensee processing and studies against CEA technical standards, connection and tripartite agreements, dedicated lines, 60-day decisions, and testing or infirm-power injection before commercial operation (p5–10).

Chapter 3 sets who may seek open access — licensees, generating companies, captive plants and consumers — and conditions such as independent feeders, common-carrier duty, exclusion of insolvents and those with more than two months' dues, and criteria for long-term versus medium/short-term access (p10–12). Chapter 4 is the procedural core. It categorises applications by system, location and duration; sets forms, fees and documents; details long-term, medium-term and short-term procedures, including bank guarantees, start-date windows, advance and day-ahead short-term applications, and electronic bidding for congested capacity (p12–24); and addresses consents, defaulters, applications by other entities and allotment priority (p24–28).

Chapter 5 sets out the charging architecture: transmission charges, scheduling and system operation charges, wheeling charges, cross-subsidy surcharge, additional surcharge, standby or grid-support charges, parallel-operation charges and restoration charges, with several rate elements left to Commission determination (p28–35). Chapter 6 covers SLDC scheduling, special energy meters, schedule revision and loss-bearing (p35–37). Chapter 7 creates an imbalance-charge settlement mechanism through a State Imbalance Pool Account and refers reactive-energy charges to the State Grid Code (p37–38).

Chapter 8 specifies billing, collection and disbursement for inter-State and intra-State transactions, late-payment surcharge, default consequences including disconnection and refusal to schedule, and a letter-of-credit payment security for long- and medium-term access (p38–42). Chapter 9 requires SLDC to publish open access information and issue monthly and annual reports (p42–43). Chapter 10 applies the consumer open access route to distribution-connected generating stations while excluding cross-subsidy and additional surcharge (p43–44).

Chapter 11 covers relinquishment and stranded-capacity compensation, capacity-availability computation, curtailment priority, approval of detailed procedures, removal of difficulties, force majeure, amendment and repeal/savings (p45–51). The schedules contain two matrices for distribution-connected and transmission-connected consumers — nodal agency, documents, time limits, charges and losses — and short-term application, approval, payment-schedule, congestion and bid formats (p52–73).

Standard name
Open Access Regulations
Primary topics
Open access, Connectivity and GNA, Open access charges

Read with this

The regulation

Consolidated copies, for reference (1)

3 more documents belong here and are not on Voltaic: 3 copies in another language.

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document