TNERC · Tamil Nadu Electricity Regulatory Commission
Intra State Open Access Regulations 2005 — consolidated re-publication, as amended up to 31-12-2010
Tamil Nadu Electricity Regulatory Commission - Intra State Open Access Regulations 2005
Consolidated copyDated 31 Dec 2009Published in the Gazette 13 Apr 2011Notification No.TNERC/ISOA/11/1-5 dated 18-03-2011
Replaced by Grid Connectivity and Intra-State Open Access Regulations, 2014
See that regulation for the date it took effect and for anything it keeps in force.
A consolidated copy of the Intra State Open Access Regulations 2005, published by TNERC for reference. It may not include the latest amendments; read it with the amendments listed for the regulation.
Summary
Summary written by software. Check the regulator's original before you rely on it.
TNERC's consolidated Intra State Open Access Regulations 2005, re-published in the Tamil Nadu Government Gazette of 13 April 2011 (Notification No.TNERC/ISOA/11/1-5 dated 18-03-2011) so the public has a single up-to-date text. The covering recitals (p2) list the five instruments folded into the reprint: the 2005 principal regulations (24.06.2005) and the amendments of 07.07.2008, 11.10.2008, 09.02.2010 and 07.01.2010 — the last being the earlier consolidation up to 31-12-2009. The consolidated text runs to 25 regulations over pp2–12, with footnotes showing the pre-amendment wording.
Regulations 1–4 set the frame: commencement on gazette publication, definitions (pp2–3), application to intra-state transmission and distribution systems including where used with the inter-state system (p3), and who may seek access — licensees, generating companies including captive plants, traders and consumers — with insolvency or dues outstanding beyond two months' billing as disqualification (p3).
Regulations 5–8 cover eligibility mechanics: continuation of existing wheeling contracts and the route into long-term access (p3); classification into short-term (one year or less) and long-term (five years or more), with non-conventional generators treated as long-term irrespective of capacity (p4); allotment priority headed by distribution licensees, then long-term, then short-term, with renewal preference and first-come-first-served fallback (p4); and the formulas the STU must use to compute available open access capacity segment-wise and substation-wise, published monthly on its website (p4). Regulation 9 (pp4–6) is the charges code — transmission/wheeling charges, cross-subsidy surcharge, additional surcharge for stranded cost under s.42(4), scheduling and system operation charges, UI pricing, reactive energy, grid availability and restoration charges — most left to later Commission determination, with captive generation for own use exempt from the surcharges.
Regulations 10–14 deal with process: STU and SLDC as nodal agencies for long- and short-term access respectively (p6); the phased roll-out of open access by consumer load (p7); the application, system-study, agreement and relinquishment procedure for long-term customers and the parallel SLDC route for short-term customers (pp7–8); and curtailment order — short-term first, distribution licensees last (p8).
Regulations 15–25 are the operating and housekeeping provisions: metering to CEA standards with main, check and special energy meters (p9); energy-loss bearing and loss posting (p9); grid-code compliance (p9); three-month payment security deposits (p10); collection and disbursement of each charge head plus billing/payment timelines in Reg 19-A (pp10–11); SLDC public reporting (p11); a nodal-agency-then-Commission grievance route (p11); and the standard difficulty-removal, force majeure, amendment and savings clauses (pp11–12).
Read with this
The regulation
- Dated 24 Jun 2005Intra State Open Access Regulations 2005
Amendments and corrections
Proposed changes (drafts with no final yet)
3 more documents belong here and are not on Voltaic: 3 copies in another language.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.