Forecasting, Scheduling and Deviation Settlement of Solar and Wind Generation Sources Regulations, 2018
Uttar Pradesh Electricity Regulatory Commission (Forecasting, Scheduling, Deviation Settlement and Related Matters of Solar and Wind Generation Sources) Regulations, 2018
RegulationDated 12 Dec 2018UPERC/Secy/Regulations/ABT (Solar & Wind)/2018/ dated 12.12.2018
Summary
Summary written by software. Check the regulator's original before you rely on it.
This is UPERC's state-level forecasting, scheduling and deviation-settlement framework for grid-connected solar and wind generation in Uttar Pradesh, made under section 181 of the Electricity Act, 2003 to support large-scale renewable integration while keeping the state grid secure, in line with the IEGC and the UP Electricity Grid Code (p1). It applies to solar (excluding rooftop solar covered by the separate UPERC RSPV Regulations) and wind plants connected to the intra-state transmission system with installed capacity of 5 MW and above, including self-consumption plants of that size; generators selling power outside the state are settled under the CERC DSM Regulations instead (p5).
Definitions and interpretation come first (pp1–4), fixing terms such as Absolute Error, Available Capacity, Deviation, Fixed Rate, Gaming, Pooling Station, Time-block and the QCA. Part 2 (pp6–7) creates the Qualified Coordinating Agency: generators at a pooling station of at least 5 MW nominate one QCA by consensus (a lone generator, or a generator of 50 MW or more connected alone, acts as its own QCA), registered with SLDC under a Detailed Procedure the SLDC must submit to the Commission for approval, then publish. The QCA is the single point of contact — one-time registration data, day-ahead and revised schedules, real-time availability and generation data, settlement with the State pool account, and de-pooling to individual generators — while liability for compliance stays with the generators.
Forecasting and scheduling (pp7–9) sets day-ahead, 15-minute-block availability and schedule submission, revision windows and daily revision caps, the option to adopt SLDC's forecast (with the error consequences borne by the generators), and a penalty mechanism for mis-declared Available Capacity. Part 3 (pp10–11) covers interface metering, telemetry and data acquisition, penalties for data failure or error, and the list of matters the Detailed Procedure must address. Part 4 (pp12–14) is the commercial core: Table-I deviation charges on Absolute Error bands, settlement through the state DSM pool, monthly accounting by SLDC, de-pooling, billing timelines with late-payment surcharge, curtailment treatment, and the IT platform linking SLDC and QCA. Part 5 (p15) gives the Commission powers to relax, issue directions and amend, and routes disputes to the Commission, to the QCA agreement, or to section 33(4) of the Act. Annexures I–III (pp17–24) supply the QCA registration format, wind and solar static-data checklists, day-ahead and revision formats, and the real-time telemetry list.
Read with this
Commencement notices and reasons
Procedures and orders made under it
Voltaic last read UPERC's website for final documents on 24 Nov 2026 (2 pages). A document UPERC issued after the page that lists it was read may not be held by Voltaic yet.
As of its reading of UPERC's website on 24 Nov 2026, Voltaic holds no later regulation that replaces this one.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.