Skip to content

TNERC · Tamil Nadu Electricity Regulatory Commission

Grid Interactive Solar PV Energy Generating Systems Regulations, 2024 — Draft

Tamil Nadu Electricity Regulatory Commission (Grid Interactive Solar PV Energy Generating Systems) Regulations, 2024

Draft regulationDated 13 Jun 2024TNERC/__________ xx-xx-2024 dated 13.06.2024

Draft

A proposal, not law. Voltaic holds no final regulation made from this draft.

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on tnerc.tn.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a draft principal regulation by the Tamil Nadu Electricity Regulatory Commission to replace its 2021 GISS Regulations and provide a single framework for grid-interactive solar PV systems, with or without battery energy storage, in Tamil Nadu. The draft was signed on 13 June 2024 and comments are invited by 15 July 2024; it will be taken up after thirty days from publication on the TNERC website and is to come into force on publication in the Tamil Nadu Government Gazette (pp1–3). It proposes to repeal the 2021 Regulations on commencement, with savings and an option for existing consumers to move to the 2024 terms (pp1, 38–39).

Regulations 1–3 set the title, territorial application and scope: the rules cover distribution licensees, eligible consumers/prosumers, generators, government/local bodies and any person using a licensee's grid for a GISS, including existing and new systems with or without BESS (pp2–3, 8). Regulation 1.3 caps applicability at contracted demand below 1 MW for net metering, group net metering, net billing/net feed-in and gross metering, and sets 5 kW and above for virtual net metering (pp2–3). Regulation 4 maps category and capacity ceilings onto five routes — net metering, group net metering, net billing/net feed-in, gross metering and virtual net metering — and specifies who can use each, how AC capacity is reckoned, ownership/possession, additional capacity and an arrears bar (pp8–12). Key thresholds include net billing/net feed-in up to 999 kW, gross metering above 150 kW up to 999 kW, and VNM from 5 kW for licensees/government/local bodies (pp9–11).

Regulations 5–6 are the operational core. They specify metering arrangements (bidirectional meters, generation meters, ToD registers, check meters, HT metering) and then set billing and accounting rules for each route: net metering with carry-forward and end-of-settlement lapse; net billing with monetary credit, refund or carry-over; gross metering at a feed-in tariff; group net metering with a priority list and sharing ratio; and VNM with line-loss, banking and wheeling deductions and end-of-period payment for unutilised energy (pp12–21). The section also deals with ToD adjustment, demand exceedance and treatment of inadvertent injection (pp20–21).

Regulations 7–9 cover technical requirements, interconnection/safety and metering infrastructure: non-discriminatory distribution-transformer-wise first-come-first-serve, DT/PT capacity limits, CEA and TN grid standards, anti-islanding and isolation, inspection and disconnection powers, liability for back-feeding, unauthorized operation and metering specifications (pp21–29). Regulation 10 sets the network/wheeling charge framework, exempts export units and provides a captive-use route with a reverse power relay (pp29–30). Regulations 11–14 add general conditions, meter-defect accounting, RPO and REC treatment by reference (pp30–32). Regulations 15–17 set the application, feasibility, approval, commissioning and agreement process, including portal obligations and timelines (pp32–38). Regulations 18–22 give the Commission directions, relaxation, amendment and removal-of-difficulties powers, and contain the repeal and savings clause (pp38–39).

The document ends with Form 1, an acknowledgement format and a model GISS connection agreement (pp40–56), followed by an Explanatory Statement that lists the changes from 2021: new GNM and VNM, revised transformer capacity criteria, simplified connectivity, a 10 kW feasibility exemption, shorter timelines, consumer meter procurement, removal of CUF-based export limits, higher inverter capacity, network-charge exemption for exports, clearer billing and battery storage (pp57–59).

Standard name
Net Metering and Rooftop Solar
Primary topics
Net metering, Net billing, Gross metering

Read with this

One more document belongs here and is not on Voltaic: a copy in another language.

Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on tnerc.tn.gov.in ↗

Report an issue with this document