TNERC · Tamil Nadu Electricity Regulatory Commission
Tamil Nadu Grid Interactive Solar PV Energy Generating Systems Regulations, 2021 — Draft
Tamil Nadu Electricity Regulatory Commission (Grid Interactive Solar PV Energy Generating Systems) Regulations, 2021
Draft regulationDated 17 Aug 2021TNERC/GISS/ dated 17.08.2021
Draft
A proposal that has since been finalised as the Grid Interactive Solar PV Energy Generating Systems (GISS) Regulations, 2021.
Summary
Summary written by software. Check the regulator's original before you rely on it.
The document is a draft TNERC regulation, issued on 17.08.2021, proposing a framework for grid-interactive solar PV systems in Tamil Nadu and inviting objections or suggestions by 01.09.2021 (p1). It is proposed under the Electricity Act, would extend statewide, and is to come into force on publication in the Tamil Nadu Government Gazette (p1).
Regulations 2–4 define the key actors and mechanisms — eligible consumers, prosumers, net metering, net billing/net feed-in, gross metering, meters and settlement periods — and set who may use each arrangement, ownership conditions and arrears restrictions (p2–7). Regulations 5–6 prescribe metering and billing: a single bidirectional meter for net metering/net billing or a separate renewable generation meter for gross metering, with time-of-day capability where relevant, and how units or money are netted, carried over or lapsed at settlement (p7–9).
Regulations 7–10 cover technical and commercial operation: non-discriminatory first-come-first-serve connection, capacity relative to sanctioned load and transformer capacity, reporting and website duties, CEA/grid-code safety and isolation requirements, responsibility for equipment, disconnection rights, metering infrastructure and network charges (p9–17). Regulations 11–14 add general conditions, exit treatment, meter-defect accounting, RPO treatment and REC ineligibility for net-metered/net-billed generation (p17–19).
Regulation 15 and Forms 1–2 set the application, registration, feasibility, approval, commissioning and agreement process, with a fee table and timelines, and include a model 25-year connection agreement (p19–34). Regulations 16–21 provide access and disconnection rules and Commission powers to direct, relax, amend and remove difficulties, with a broad supersession of earlier regulations and orders and savings for actions already taken (p22–24). An explanatory statement links the draft to network-cost recovery, consumer rules and the need for net-feed-in/gross-metering tariffs (p35).
Read with this
The regulation
Proposed changes (drafts with no final yet)
One more document belongs here and is not on Voltaic: a copy in another language.
Voltaic last read TNERC's website for final documents on 29 Sep 2026 and for drafts on 24 Nov 2026. A document TNERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.