Determination of Open Access Charges Regulations, 2006
Orissa Electricity Regulatory Commission (Determination of Open Access Charges) Regulations, 2006
RegulationDated 6 Jun 2006No.OERC-JD (EA)-233/2005 dated Dated the 6th June, 2006
Replaced by Terms and Conditions of Intra-State Open Access Regulations, 2020
See that regulation for the date it took effect and for anything it keeps in force.
Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed regulations shall be deemed to have been done or purported to have been done under these regulations.”
Summary
Summary written by software. Check the regulator's original before you rely on it.
A principal regulation of the Orissa Electricity Regulatory Commission framing the charges payable by open access customers for using the intra-state transmission and distribution systems. It is issued as a notification dated 6 June 2006 under s.42(2) and s.42(4) and ss.39, 40, 86 read with s.181 of the Electricity Act, 2003, and comes into force on publication in the Official Gazette (p1). It applies to open access customers within the meaning of s.2(37) and s.2(19) of the Act, and is expressly to be read with the OERC (Terms & Conditions for Open Access) Regulations, 2005 (p1, p3, p8).
Chapter I (p1–2) gives the short title, extent, commencement and a definitions set covering applicants, direct and embedded customers, existing customers, nodal agency, open access customer, SLDC, STU and transmission customer. Chapter II (p2–7) is the operative core. It specifies transmission and wheeling charges on a full-cost basis to be determined by the Commission as part of tariff, including the postage-stamp approach to per-unit cost, treatment of dedicated lines used exclusively by an open access customer, network augmentation funding, interstate transmission charges alongside wheeling, and separate rate methodologies for long-term, short-term and very-short-term (sub-day) transmission customers with a sharing arrangement between short-term receipts and long-term payers (p3–4). It then specifies cross-subsidy surcharge (avoided-cost method, computed by the licensee and approved by the Commission, to be progressively reduced and eliminated), additional surcharge for the licensee's obligation to supply (triggered only on demonstrated stranded fixed costs), scheduling and system operation charges, reactive energy charges settled through the STU pool and not apportioned to embedded customers, short-term access charges by bidding under the 2005 Regulations, UI charges with ERLDC/SLDC segregation, and miscellaneous penal and meter-rent charges (p4–7).
Chapter III (p7–8) fixes the point of supply at the customer's interface point, allocates average technical losses to be compensated by extra injection (loss data to be posted on the SLDC website), cross-refers payment terms to the 2005 Regulations, and preserves existing open access arrangements for the life of the existing agreement subject to payment of the new charges. Chapter IV (p8–9) covers the Commission's power to issue orders and practice directions, a savings clause preserving the Commission's latitude, and a difficulty-removal power.
Read with this
Procedures and orders made under it
- Dated 22 Aug 2008Revised Order on Open Access Charges, 2008
One more document belongs here and is not on Voltaic: a commencement notice or statement of reasons not held as English text.
Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.
Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.