OERC · Odisha Electricity Regulatory Commission

Revised Order on Open Access Charges, 2008

In the matter of: Approval of Open Access Charges (Transmission/Wheeling Charges, Surcharge and additional surcharge applicable to open access customers for use of intra-state transmission/distribution system) in accordance with Section 39 and 42 of the Electricity Act, 2003 read with the provisions of chapter II (Charges for Open Access) of OERC (Determination of Open Access Charges) Regulations, 2006.

OrderDated 22 Aug 2008In force from 1 Apr 2008Case Nos.66, 67, 68 & 69 of 2006 dated 22.08.2008

Replaced by Terms and Conditions of Intra-State Open Access Regulations, 2020

See that regulation for the date it took effect and for anything it keeps in force.

Made under the Determination of Open Access Charges Regulations, 2006.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed regulations shall be deemed to have been done or purported to have been done under these regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on orierc.org ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is a one-page suo motu revised order from OERC dated 22.08.2008 (p1). It corrects typographical and calculation errors in the Commission's common order dated 29.03.2008 in Case Nos. 66, 67, 68 & 69 of 2006 on open access charges (p1). The substantive correction is SOUTHCO's wheeling charge, recalculated to 85.00 p/u in place of 67.30 p/u; the EHT surcharge is left unchanged (p1). It directs a figure substitution in para-38 Table 4 and replacement of the sixth row of para-38 Table 5 (p1). The order is to be served on SOUTHCO and other parties, published in the same Oriya and English newspapers as the original, and posted on the Commission's website (p1). It applies retrospectively from 01.04.2008 (p1).

Standard name
Open Access Regulations
Primary topics
Open access charges

Read with this

The regulation

One more document belongs here and is not on Voltaic: a commencement notice or statement of reasons not held as English text.

Voltaic last read OERC's website for final documents between 24 Nov 2026 and 26 Nov 2026 (9 pages) and for drafts on 21 Nov 2026. A document OERC issued after the page that lists it was read may not be held by Voltaic yet.