PSERC · Punjab State Electricity Regulatory Commission

Punjab Renewable Purchase Obligation and its Compliance Regulations, 2011

Punjab State Electricity Regulatory Commission (Renewable Purchase Obligation and its compliance) Regulations, 2011

RegulationDated 3 Jun 2011No.PSERC/Secy./Reg./55 dated The 03,June, 2011

Replaced by Punjab Renewable Purchase Obligation and its Compliance Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed Regulations shall deemed to have been done or purported to have been done under these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

This is PSERC's first standalone regulation on the Renewable Purchase Obligation (RPO) in Punjab, issued as Notification No. PSERC/Secy./Reg./55 dated 3 June 2011 (p1). It applies throughout the State of Punjab and comes into force on the date of publication in the Official Gazette, though that Gazette date is not printed in the text (p1).

Regulation 2 defines the working vocabulary the rest of the instrument depends on, including 'obligated entity', 'renewable energy sources', 'renewable purchase obligation', 'Certificate', 'floor price', 'forbearance price', 'Central Agency', 'State Agency' and 'Year' (p1–3). It deliberately borrows the meaning of anything undefined from the Electricity Act and from CERC or PSERC regulations (p3).

Regulation 3 is the operative core. It requires every obligated entity to purchase a Commission-specified minimum share of its electricity consumption from renewable sources, measured at the entity's boundary, with a carve-out that a specified portion must come from solar generation. The year-wise minimum total, solar and non-solar percentages for 2011-12 through 2014-15 are set out in Table-1 (p3–4). Purchases already being made count towards the obligation, existing PPAs consented to by the Commission run to their stated validity even if they exceed the target, and self-generation consumed in the licensee's own area is counted. The Commission may revise the targets on its own motion, on the State Agency's recommendation, or on application, and these RPOs supersede any RPO in other PSERC regulations or orders (p4–5).

Regulation 4 makes CERC renewable energy certificates (RECs) the valid instrument for discharging the obligation, with solar obligations satisfiable only by solar certificates and non-solar obligations by non-solar certificates, and requires certificates to be deposited with the Commission per the Central Agency's procedure (p5–6). Regulation 5 provides for a designated State Agency handling accreditation and registration, quarterly compliance reporting, its own liability to penalty under section 142 if it fails to enable sufficient renewable capacity, and its replacement by order of the Commission (p6–7).

Regulation 6 deals with default: a fund to be created by the obligated entity equivalent to the shortfall valued at the CERC forbearance price, procurement of certificates out of that fund, a 15-day deposit deadline whose breach puts a distribution licensee in breach of its licence, and penalty under section 142 — with a route to seek carry-forward of a shortfall to the next year, reviewed over a three-year period (p7–8). Regulations 7 to 9 preserve the Commission's inherent powers, allow it to remove difficulties by order, and to amend the regulations at any time (p8–9).

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO), Renewable energy certificates (REC), Compliance and reporting

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page