Renewable Purchase Obligation and its compliance (Amendment-3) Regulations, 2021

Punjab State Electricity Regulatory Commission (Renewable Purchase Obligation and its compliance) (Amendment-3) Regulations, 2021

AmendmentDated 26 Mar 2021Published in the Gazette 26 Mar 2021No. PSERC/Secy./Reg./156.- dated The 26th March, 2021

Replaced by Punjab Renewable Purchase Obligation and its Compliance Regulations, 2022

See that regulation for the date it took effect and for anything it keeps in force.

Amends the Punjab Renewable Purchase Obligation and its Compliance Regulations, 2011.

Saving clause of the regulation that replaces it: “Notwithstanding such repeal, anything done or purported to have been done under the repealed Regulations shall deemed to have been done or purported to have been done under these Regulations.”

Full text needs a Voltaic key. A key opens the full text of 20 different documents a day, on this site and in your AI together. The summary, the reading list and the regulator's original are open to everyone.

Enter your key

Your key is the last part of the connector address we sent you. This browser remembers it until you choose to forget it. No key yet? Ask for one at hello@voltaicplatform.com.

Ask for a keyOpen the regulator's original on pserc.punjab.gov.in ↗

Summary

Summary written by software. Check the regulator's original before you rely on it.

A one-page notification by which the Punjab State Electricity Regulatory Commission makes the third amendment to its 2011 Renewable Purchase Obligation (RPO) Regulations (p1). Clause 1 gives the short title, provides that the amendment takes effect from the date of publication in the Official Gazette, and extends it to the whole of Punjab (p1). Clause 2 is the operative provision: it inserts a new proviso at the end of Regulation 3(1) of the Principal Regulations, dealing with how the RPO level is fixed for Captive Power Plants (p1).

The proviso distinguishes CPPs by commissioning date, tying each plant's RPO to the level specified by the Commission for the relevant year rather than a single uniform level, and provides that where a CPP's capacity is augmented, the augmented capacity carries the RPO applicable to the year of augmentation (p1). Nothing else in the Principal Regulations is touched.

Standard name
RPO Regulations
Primary topics
Renewable purchase obligation (RPO / RCO)

Read with this

Voltaic last read PSERC's website for final documents on 26 Nov 2026. A document PSERC issued after the page that lists it was read may not be held by Voltaic yet.

How to read a Voltaic page

Full text on Voltaic needs a key: enter your key near the top of this page. The regulator's original is open to everyone.

Open the regulator's original on pserc.punjab.gov.in ↗

Report an issue with this document